6711 N QUAKERTOWN AVE 91306
Certificate Information: 6711 N QUAKERTOWN AVE 91306
- Application / Permit
- 22016-20000-22352
- Plan Check / Job No.
- B22VN11483
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Converting existing Garage to ADU 358 sq.ft
- Permit Issued
- Issued on 2/8/2023
- Issuing Office
- Current Status
- Issued on 2/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 8/6/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 8/16/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 11/29/2022 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 1/6/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 2/1/2023 | MARCELA FRANQUEZ |
| Issued | 2/8/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 1/9/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/29/2023 | Corrections Issued | ROBERT SUNSERI |
| Underground Mechanical | 4/6/2023 | Approved | ROBERT SUNSERI |
| Footing/Foundation/Slab | 4/13/2023 | Approved | EMIL ALEXANDRIAN |
| Structural Steel Frame | 4/13/2023 | Approved | EMIL ALEXANDRIAN |
| Deputy Drilled-In Anchors | 5/8/2023 | Approved | EMIL ALEXANDRIAN |
| BUILDING-Rough-Frame | 5/15/2023 | Corrections Issued | ROBERT SUNSERI |
| ELECTRICAL-Rough | 5/15/2023 | Corrections Issued | ROBERT SUNSERI |
| BUILDING-Rough-Frame | 6/2/2023 | Not Ready for Inspection | ROBERT SUNSERI |
| ELECTRICAL-Rough | 6/2/2023 | Not Ready for Inspection | ROBERT SUNSERI |
| Special/Order Compliance | 6/2/2023 | Approved | ROBERT SUNSERI |
| BUILDING-Rough-Frame | 7/6/2023 | Not Ready for Inspection | ARA SINANIAN |
| PLUMBING-Rough | 7/6/2023 | Approved | ARA SINANIAN |
| BUILDING-Rough-Frame | 7/18/2023 | Partial Approval | ARA SINANIAN |
| ELECTRICAL-Rough | 7/18/2023 | Approved | ARA SINANIAN |
| Insulation | 8/1/2023 | Approved | ARA SINANIAN |
| Interior/Exterior Lathing | 8/1/2023 | Approved | ARA SINANIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Approved | ARA SINANIAN |
| Drywall Nailing | 8/9/2023 | Approved | ARA SINANIAN |
| Sewer | 8/17/2023 | Approved | ARA SINANIAN |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | ARA SINANIAN |
| ELECTRICAL-Final | 9/19/2023 | Not Ready for Inspection | ARA SINANIAN |
| Final | 9/19/2023 | Not Ready for Inspection | ARA SINANIAN |
| PLUMBING-Final | 9/19/2023 | Not Ready for Inspection | ARA SINANIAN |
| Smoke Detectors | 9/19/2023 | Approved | ARA SINANIAN |
| Final | 10/3/2023 | Conditional Approval | ARA SINANIAN |