15938 W HART ST 91406

Certificate Information: 15938 W HART ST 91406

Application / Permit
22016-20000-21699
Plan Check / Job No.
B22VN11228
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Convert the existing 18' x 20' 2-car garage into a 360 SQ FT ADU PER WFPP
Permit Issued
Issued on 8/19/2022
Issuing Office
Current Status
CofO Issued on 5/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/22/2022 APPLICANT
Assigned to Plan Check Engineer 7/29/2022 JOSEPH RAFOLS
Corrections Issued 7/29/2022 JOSEPH RAFOLS
Plan Check Approved 8/15/2022 JOSEPH RAFOLS
Issued 8/19/2022 APPLICANT
CofO in Progress 5/5/2023 RAUL OLAGI
CofO Issued 5/8/2023 MICHAEL SMITH
Permit Finaled 5/8/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 8/1/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/1/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 8/2/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Maven Associates Inc The; Lic. No.: 1085625-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/2/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 12/12/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 1/25/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 1/25/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 1/25/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 1/25/2023 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 2/10/2023 Corrections Issued RAUL OLAGI
Special/Order Compliance 2/10/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 2/27/2023 Not Ready for Inspection RAUL OLAGI
ELECTRICAL-Rough 2/27/2023 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Partial Approval RAUL OLAGI
HVAC-Rough 2/27/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 2/27/2023 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 3/2/2023 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 3/2/2023 Approved RAUL OLAGI
Green Building Rough 3/2/2023 Approved RAUL OLAGI
HVAC-Rough 3/2/2023 Partial Approval RAUL OLAGI
PLUMBING-Rough 3/2/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 3/7/2023 Approved MATTHEW NELSON
Insulation 3/7/2023 Approved MATTHEW NELSON
Interior/Exterior Lathing 3/7/2023 Corrections Issued MATTHEW NELSON
Shower Pan 3/7/2023 Approved MATTHEW NELSON
Drywall Nailing 3/10/2023 Approved JOHN KIDWELL
Interior/Exterior Lathing 3/10/2023 Partial Approval JOHN KIDWELL
Sewer 3/30/2023 Corrections Issued RAUL OLAGI
Sewer 4/3/2023 Approved RAUL OLAGI
Final 4/20/2023 Not Ready for Inspection RAUL OLAGI
Green Building Final 4/20/2023 Not Ready for Inspection RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 4/20/2023 Not Ready for Inspection RAUL OLAGI
Final 4/25/2023 Corrections Issued RAUL OLAGI
Green Building Final 4/25/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 4/25/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 4/25/2023 Approved RAUL OLAGI
Final 5/1/2023 No Access for Inspection RAUL OLAGI
Final 5/5/2023 OK to Issue CofO RAUL OLAGI