2130-2132 S GREENFIELD AVE 90025

Certificate Information: 2130-2132 S GREENFIELD AVE 90025

Application / Permit
22016-20000-21604
Plan Check / Job No.
B22VN11160
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE INTO JUNIOR ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). AND 65852.22. REMODEL EX. SFD TO CONVERT PORTION OF ATT. GARAGE TO BATHROOM. ADD NEW BATHROOM AND CLOSET AT EX. BEDROOM. REMODEL EX. BATHROOM. REFRAME/ REMODEL KITCHEN AREA. REPLACE ALL DOORS AND WINDOWS, REMOVE WALLS, REPLACE DRYWALL AND INSULATION. RE-ROOF BLDG. WORK PER ENGINEER.
Permit Issued
Issued on 9/16/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/20/2022 APPLICANT
Assigned to Plan Check Engineer 7/27/2022 SERGIO MUNIZ
Corrections Issued 7/28/2022 SERGIO MUNIZ
Applicant returned to address corrections 9/1/2022 ROSENDO MEDINA
Plan Check Approved 9/16/2022 HAYATO TSUCHIYA
Issued 9/16/2022 APPLICANT
CofO in Progress 3/29/2024 JESUS PINEDA
Permit Finaled 4/2/2024 DANIEL ORRANTE
CofO Issued 4/2/2024 DANIEL ORRANTE
Permit Finaled 4/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

ZA Case Cleared 8/12/2022 NATHAN ROMINE
Address approval Cleared 8/14/2022 STEVEN JIN
Sewer availability Cleared 8/14/2022 STEVEN JIN
Grading Pre-Inspection Cleared 9/1/2022 SERGIO MUNIZ
Specific Plan Cleared 9/1/2022 DANG NGUYEN
Eng Process Fee Ord 176,300 Cleared 9/2/2022 KATHLEEN LEE

Contact Information

Contractor Builtright Construction; Lic. No.: 847796-B 6603 INDEPENDENCE AVENUE A      CANOGA PARK, CA 91303
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/26/2022 Approved CLAYTON GRAHAM
PLUMBING-Rough 10/21/2022 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 11/22/2022 Corrections Issued ASHLEY THOMPSON
HVAC-Rough 11/22/2022 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 11/22/2022 Corrections Issued ASHLEY THOMPSON
BUILDING-Rough-Frame 11/29/2022 Corrections Issued ASHLEY THOMPSON
Green Building Rough 11/29/2022 Not Ready for Inspection ASHLEY THOMPSON
Wood Frame 11/29/2022 Approved ASHLEY THOMPSON
Insulation 12/9/2022 Approved JEREMY TODD
Interior/Exterior Lathing 12/9/2022 Not Ready for Inspection JEREMY TODD
Shower Pan 12/9/2022 Not Ready for Inspection JEREMY TODD
Interior/Exterior Lathing 12/13/2022 Not Ready for Inspection ASHLEY THOMPSON
Shower Pan 12/13/2022 Not Ready for Inspection ASHLEY THOMPSON
Drywall Nailing 12/15/2022 Partial Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 12/15/2022 Partial Approval ASHLEY THOMPSON
Shower Pan 12/15/2022 Approved ASHLEY THOMPSON
Drywall Nailing 12/22/2022 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 12/22/2022 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 12/14/2023 Approved BEN MOLSTAD
Final 12/14/2023 Not Ready for Inspection BEN MOLSTAD
Green Building Final 12/14/2023 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 12/14/2023 Approved BEN MOLSTAD
HVAC-Final 12/14/2023 Corrections Issued BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 12/14/2023 SGSOV Approved BEN MOLSTAD
Smoke Detectors 12/14/2023 Approved BEN MOLSTAD
Final 1/11/2024 Partial Approval BEN MOLSTAD
Green Building Final 1/11/2024 Approved BEN MOLSTAD
Final 3/29/2024 OK to Issue CofO JESUS PINEDA