6950-6952 N NAGLE AVE 91605
Certificate Information: 6950-6952 N NAGLE AVE 91605
- Application / Permit
- 22016-20000-21560
- Plan Check / Job No.
- B22VN11146
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT THE (E) 20' x 20'6" ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) - ALL WORK PER WOOD FRAME PROVISIONS AND ENGINEER DETAIL
- Permit Issued
- Issued on 8/12/2022
- Issuing Office
- Current Status
- CofO Issued on 3/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/27/2022 | JEFFREY TANGONAN |
| Corrections Issued | 7/27/2022 | JEFFREY TANGONAN |
| Issued | 8/12/2022 | APPLICANT |
| CofO in Progress | 12/7/2022 | ARAM AVEDISIAN |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
| CofO Issued | 3/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/1/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/2/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Ramirez Construction Co; Lic. No.: 1023300-B | 2636 PINE PL SOUTH GATE, CA 90280 |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/23/2022 | Conditional Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 8/26/2022 | Approved | ALAN MORELOS |
| PLUMBING-Rough | 8/26/2022 | Partial Approval | ALAN MORELOS |
| Sewer | 8/26/2022 | Approved | ALAN MORELOS |
| ELECTRICAL-Rough | 9/12/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 9/12/2022 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 9/12/2022 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 9/15/2022 | Approved | RAFAEL CORTES |
| Insulation | 9/15/2022 | Approved | RAFAEL CORTES |
| Shower Pan | 9/15/2022 | Approved | RAFAEL CORTES |
| Drywall Nailing | 9/21/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 9/21/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/21/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 12/7/2022 | Approved | ARAM AVEDISIAN |
| Final | 12/7/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 12/7/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 12/7/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 12/7/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 12/7/2022 | Approved | ARAM AVEDISIAN |