10740 W SYLVAN ST 91606
Certificate Information: 10740 W SYLVAN ST 91606
- Application / Permit
- 22016-20000-21544
- Plan Check / Job No.
- B22VN11133
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT PORTION OF DWELLING AND DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/18/2022 | SELLA BENYAMIN |
| Corrections Issued | 8/25/2022 | SELLA BENYAMIN |
| Quality Review Completed | 8/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 10/5/2022 | APPLICANT |
| Plan Check Approved | 10/27/2022 | SELLA BENYAMIN |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 10/11/2024 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
| CofO Issued | 10/23/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/23/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/11/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/11/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/20/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 5/4/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 5/10/2023 | Approved | JOHN HAYES |
| Special/Order Compliance | 5/31/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 9/14/2023 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 10/12/2023 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 10/12/2023 | Corrections Issued | JOHN HAYES |
| Wood Frame | 11/9/2023 | Approved | JOHN HAYES |
| Insulation | 11/17/2023 | Approved | THOMAS FINNILA |
| Drywall Nailing | 11/21/2023 | Approved | RUBEN SALAS |
| Drywall Nailing | 11/28/2023 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 8/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 8/23/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 8/23/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 9/30/2024 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 9/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/30/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |