5514 W 82ND ST 90045

Certificate Information: 5514 W 82ND ST 90045

Application / Permit
22016-20000-21449
Plan Check / Job No.
B22VN11062
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DET. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A).
Permit Issued
Issued on 8/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 7/27/2022 JESSE ARELLANO
Corrections Issued 7/28/2022 JESSE ARELLANO
Building Plans Picked Up 8/1/2022 APPLICANT
Issued 8/29/2022 APPLICANT
CofO in Progress 2/18/2023 RICHARD STEINBACH
Permit Finaled 2/25/2023 DANIEL ORRANTE
CofO Issued 2/25/2023 DANIEL ORRANTE
Permit Finaled 2/25/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/11/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/11/2022 DINAH GARIN
Sewer availability Cleared 8/11/2022 DINAH GARIN
Green Code Cleared 8/29/2022 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/1/2022 Approved BOBBY KEY
Deputy Drilled-In Anchors 9/2/2022 Conditional Approval RICHARD STEINBACH
PLUMBING-Rough 9/6/2022 Partial Approval BOBBY KEY
Underground Mechanical 9/12/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 9/27/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 9/27/2022 Partial Approval BOBBY KEY
HVAC-Rough 9/27/2022 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 9/27/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 10/3/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 10/3/2022 Approved BOBBY KEY
Underground Mechanical 10/3/2022 Approved BOBBY KEY
HVAC-Rough 10/7/2022 Partial Approval BOBBY KEY
Insulation 10/7/2022 Conditional Approval BOBBY KEY
Interior/Exterior Lathing 10/7/2022 Partial Approval BOBBY KEY
BUILDING-Rough-Frame 10/13/2022 Approved BOBBY KEY
Green Building Rough 10/13/2022 Approved BOBBY KEY
Insulation 10/13/2022 Approved BOBBY KEY
Interior/Exterior Lathing 10/13/2022 Partial Approval BOBBY KEY
Shower Pan 10/13/2022 Approved BOBBY KEY
Drywall Nailing 10/20/2022 Approved BOBBY KEY
Interior/Exterior Lathing 10/20/2022 Approved BOBBY KEY
ELECTRICAL-Final 2/17/2023 Approved BOBBY KEY
Final 2/17/2023 OK to Issue CofO BOBBY KEY
Green Building Final 2/17/2023 Approved BOBBY KEY
HVAC-Final 2/17/2023 Approved BOBBY KEY
PLUMBING-Final 2/17/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 2/17/2023 SGSOV Approved BOBBY KEY
Smoke Detectors 2/17/2023 Approved BOBBY KEY