1186 E 52ND ST 90011

Certificate Information: 1186 E 52ND ST 90011

Application / Permit
22016-20000-21358
Plan Check / Job No.
B22VN11039
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 80' X 18' DETACHED 8-CAR GARAGE INTO (N)ONE STORY DETACHED ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 8/18/2023
Issuing Office
Valley
Current Status
CofO Corrected on 10/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 7/19/2022 GURUNATH NESARAJAH
Corrections Issued 7/20/2022 GURUNATH NESARAJAH
Building Plans Picked Up 7/20/2022 APPLICANT
Applicant returned to address corrections 12/5/2022 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/10/2023 JESSE ARELLANO
Applicant returned to address corrections 4/7/2023 HAYATO TSUCHIYA
Applicant returned to address corrections 5/5/2023 MADISON ODELL
Plan Check Approved 5/16/2023 RAMA DABADGE
Issued 8/18/2023 APPLICANT
CofO in Progress 6/18/2024 JOSEPH MCGARRY
CofO Issued-Status Void 6/25/2024 DEROLD HAUFF
Permit Finaled-Status Void 6/25/2024 DEROLD HAUFF
Re-Activate Permit 10/10/2024 DEROLD HAUFF
Permit Finaled 10/10/2024 DEROLD HAUFF
CofO Corrected 10/10/2024 DEROLD HAUFF
Permit Finaled 10/10/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/19/2022 TREVOR QUAN
Sewer availability Cleared 9/19/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 9/21/2022 TREVOR QUAN
Construction near power lines Cleared 11/9/2022 RIDWAN HARDY
Construction within easement Cleared 11/9/2022 RIDWAN HARDY

Contact Information

Contractor Wdg Construction Inc; Lic. No.: 1096820-B 5459 MERIDIAN PL      BONSALL, CA 92003
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/18/2023 Conditional Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 9/20/2023 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/20/2023 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 9/20/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 9/20/2023 Approved ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 11/27/2023 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 11/29/2023 Corrections Issued ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 12/1/2023 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/14/2023 Corrections Issued ALEJANDRO DE ARTOLA
Reinforced Concrete Frame 12/14/2023 Partial Approval ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 12/18/2023 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Partial Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/18/2024 Approved ALEJANDRO DE ARTOLA
Deputy Wood Construction 1/22/2024 Conditional Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 2/8/2024 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/21/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 2/21/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 2/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 2/28/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 2/28/2024 Approved JOSH MEISTER
Deputy Wood Construction 3/1/2024 Conditional Approval ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/5/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/5/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 3/8/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/27/2024 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 3/27/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 4/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 4/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 4/26/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 4/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 4/26/2024 SGSOV Not Ready ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 5/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 5/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 5/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 5/30/2024 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 5/30/2024 Approved ALEJANDRO DE ARTOLA
Final 6/14/2024 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 6/14/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 6/14/2024 SGSOV Approved JOSEPH MCGARRY