7058 N MCLENNAN AVE 91406
Certificate Information: 7058 N MCLENNAN AVE 91406
- Application / Permit
- 22016-20000-21177
- Plan Check / Job No.
- B22VN10973
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL WITH THE REMOVAL OF LOAD BEARING WALLS AT KITCHEN/DINING ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 8/16/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/9/2023
Permit Application Status History
| Submitted | 8/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 8/5/2022 | LUISANGEL VALENZUELA |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
| Plan Check Approved | 8/16/2022 | OMAR GARNICA |
| Issued | 8/16/2022 | APPLICANT |
| Permit Finaled | 8/8/2023 | RAUL OLAGI |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | T & N Remodeling Inc; Lic. No.: 1063782-B | C6200 VENTURA BLVD STE 424 ENCINO, CA 91436 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| Footing/Foundation/Slab | 9/14/2022 | Corrections Issued | RAUL OLAGI |
| Reinforced Concrete Frame | 9/14/2022 | Not Ready for Inspection | RAUL OLAGI |
| Excavation/Setback/Form/Re-Bar | 9/19/2022 | Approved | RAUL OLAGI |
| Footing/Foundation/Slab | 9/19/2022 | Approved | RAUL OLAGI |
| Wood Frame | 10/19/2022 | Not Ready for Inspection | RAUL OLAGI |
| Wood Frame | 12/9/2022 | Approved | RAUL OLAGI |
| Final | 7/10/2023 | Corrections Issued | RAUL OLAGI |
| Smoke Detectors | 7/10/2023 | Approved | RAUL OLAGI |
| Final | 8/8/2023 | Permit Finaled | RAUL OLAGI |