7960 N WOODLAKE AVE 91304

Certificate Information: 7960 N WOODLAKE AVE 91304

Application / Permit
22016-20000-21161
Plan Check / Job No.
B22VN10966
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' 8" X 21' 8" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 2/16/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/18/2022 PINANK PATEL
Corrections Issued 7/19/2022 PINANK PATEL
Building Plans Picked Up 7/26/2022 APPLICANT
Plan Check Approved 1/23/2023 GURUNATH NESARAJAH
Issued 2/16/2023 APPLICANT
CofO in Progress 8/29/2023 CHRIS CHRISTENSEN
Permit Finaled 9/1/2023 JOHN JANSON
CofO Issued 9/1/2023 JOHN JANSON
Permit Finaled 9/1/2023 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 1/12/2023 RIDWAN HARDY
Address approval Cleared 1/18/2023 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 1/18/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 1/18/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 21757 DEVONSHIRE ST.   SUITE 3    CANOGA PARK, CA 91311

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/9/2023 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 3/13/2023 Approved CHRIS CHRISTENSEN
Sewer 3/13/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Sewer 3/20/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/28/2023 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/28/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 3/28/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/28/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 3/28/2023 Approved CHRIS CHRISTENSEN
Special/Order Compliance 3/28/2023 Partial Inspection MORRIS JACKSON
BUILDING-Rough-Frame 4/4/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 4/4/2023 Approved CHRIS CHRISTENSEN
HVAC-Rough 4/4/2023 Approved CHRIS CHRISTENSEN
Insulation 4/4/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/4/2023 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 4/14/2023 Approved JUSTIN HAWLEY
Shower Pan 4/14/2023 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/21/2023 Approved CHRIS CHRISTENSEN
Final 6/22/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 6/22/2023 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 6/22/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 7/31/2023 Approved CHRIS CHRISTENSEN
HVAC-Final 7/31/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Final 7/31/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/31/2023 SGSOV Approved CHRIS CHRISTENSEN
Final 8/14/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 8/14/2023 Approved CHRIS CHRISTENSEN
Final 8/28/2023 OK to Issue CofO CHRIS CHRISTENSEN
Service/Power Release 8/28/2023 Approved CHRIS CHRISTENSEN