7960 N WOODLAKE AVE 91304
Certificate Information: 7960 N WOODLAKE AVE 91304
- Application / Permit
- 22016-20000-21161
- Plan Check / Job No.
- B22VN10966
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' 8" X 21' 8" DETACHED 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 2/16/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2022 | PINANK PATEL |
| Corrections Issued | 7/19/2022 | PINANK PATEL |
| Building Plans Picked Up | 7/26/2022 | APPLICANT |
| Plan Check Approved | 1/23/2023 | GURUNATH NESARAJAH |
| Issued | 2/16/2023 | APPLICANT |
| CofO in Progress | 8/29/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 9/1/2023 | JOHN JANSON |
| CofO Issued | 9/1/2023 | JOHN JANSON |
| Permit Finaled | 9/1/2023 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/12/2023 | RIDWAN HARDY |
| Address approval | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 1/18/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/13/2023 | Approved | CHRIS CHRISTENSEN |
| Sewer | 3/13/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Sewer | 3/20/2023 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/28/2023 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 3/28/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/28/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/28/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/28/2023 | Approved | CHRIS CHRISTENSEN |
| Special/Order Compliance | 3/28/2023 | Partial Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 4/4/2023 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 4/4/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 4/4/2023 | Approved | CHRIS CHRISTENSEN |
| Insulation | 4/4/2023 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 4/4/2023 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/14/2023 | Approved | JUSTIN HAWLEY |
| Shower Pan | 4/14/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 4/21/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 6/22/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 6/22/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2023 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 6/22/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 7/31/2023 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 7/31/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 7/31/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/31/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 8/14/2023 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 8/14/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 8/28/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 8/28/2023 | Approved | CHRIS CHRISTENSEN |