8215-8217 N NOBLE AVE 91402

Certificate Information: 8215-8217 N NOBLE AVE 91402

Application / Permit
22016-20000-20919
Plan Check / Job No.
B22VN10907
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 19'-8" x 10'-1" ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22
Permit Issued
Issued on 9/1/2022
Issuing Office
Valley
Current Status
Issued on 9/1/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/19/2022 JESSE ARELLANO
Corrections Issued 7/20/2022 JESSE ARELLANO
Applicant returned to address corrections 8/22/2022 ALFRED RAMIREZ
Plan Check Approved 9/1/2022 ALEC MOUSAKHANIAN
Issued 9/1/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/1/2022 ROMAN GUTIERREZ
Sewer availability Cleared 8/1/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/12/2022 ROMAN GUTIERREZ
Green Code Cleared 8/22/2022 JESSE ARELLANO

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/20/2022 Corrections Issued WILLIAM WREN
Excavation/Setback/Form/Re-Bar 9/26/2022 Approved WILLIAM WREN
PLUMBING-Rough 10/12/2022 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 10/24/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 10/24/2022 Approved GREGG CUMMINGS
Special/Order Compliance 10/24/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 11/4/2022 Corrections Issued GREGG CUMMINGS
BUILDING-Rough-Frame 11/16/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 11/16/2022 Not Ready for Inspection GREGG CUMMINGS
Insulation 11/16/2022 Not Ready for Inspection GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 12/6/2022 Partial Approval GREGG CUMMINGS
HVAC-Rough 12/6/2022 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 12/22/2022 Partial Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 12/22/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 12/22/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 1/10/2023 Partial Approval CHRISTOPHER DELLEFIELD
Wood Frame 1/10/2023 OK to Expire Permit CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 1/13/2023 Approved GREGG CUMMINGS
Green Building Rough 1/13/2023 Approved GREGG CUMMINGS
MERV13>=Rough 1/13/2023 Approved GREGG CUMMINGS
Insulation 1/20/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 1/23/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 1/23/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 1/30/2023 Approved CHRISTOPHER DELLEFIELD
Shower Pan 2/14/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 2/24/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 4/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 4/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 4/20/2023 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 4/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
MERV13>=Final 4/20/2023 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 4/20/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 6/2/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Final 6/2/2023 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Final 6/2/2023 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 6/2/2023 Approved CHRISTOPHER DELLEFIELD