5510-5512 N BURNET AVE 91411

Certificate Information: 5510-5512 N BURNET AVE 91411

Application / Permit
22016-20000-20917
Plan Check / Job No.
B22VN10905
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 21'-10" X 20'-0" ATTACHED 2-CAR GARAGE TO ADU UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22, AND INTERIOR REMODEL TO (E) SFD TO REVISE ENTIRE FLOOR PLAN LAYOUT. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 7/28/2022
Issuing Office
Valley
Current Status
Permit Finaled on 1/2/2024

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/15/2022 GURUNATH NESARAJAH
Corrections Issued 7/17/2022 GURUNATH NESARAJAH
Building Plans Picked Up 7/19/2022 APPLICANT
Issued 7/28/2022 APPLICANT
Permit Finaled 1/2/2024 JUAN VALENZUELA

Permit Application Clearance Information

Address approval Cleared 7/20/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/20/2022 ROMAN GUTIERREZ
Sewer availability Cleared 7/20/2022 ROMAN GUTIERREZ
ZI Cleared 7/21/2022 DANG NGUYEN

Contact Information

Architect Miller,, Michael; Lic. No.: C26956 12756 MITCHELL AVE      LOS ANGELES, CA 90066
Contractor Mega Builders Inc; Lic. No.: 898347-B 18375 VENTURA BLVD SUITE 520      TARZANA, CA 91356

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Rough-Elec/Plmb/HVAC 8/26/2022 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Rough 8/29/2022 Corrections Issued CALEB MEISTER
HVAC-Rough 8/29/2022 Corrections Issued CALEB MEISTER
PLUMBING-Rough 8/29/2022 Approved CALEB MEISTER
Drywall Nailing 9/6/2022 Approved JACK KARGODORIAN
ELECTRICAL-Rough 9/6/2022 Approved JACK KARGODORIAN
Insulation 9/6/2022 Corrections Issued JACK KARGODORIAN
Shower Pan 9/6/2022 Approved JACK KARGODORIAN
Interior/Exterior Lathing 9/14/2022 Partial Approval JACK KARGODORIAN
Interior/Exterior Lathing 9/21/2022 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 9/23/2022 Partial Approval JACK KARGODORIAN
Insulation 9/26/2022 No Access for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/6/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 12/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 12/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 12/6/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 12/6/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 12/6/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 12/6/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 12/6/2022 Approved CHRISTOPHER DELLEFIELD
Final 12/15/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 1/9/2023 Conditional Approval JOHN COLEMAN
Final 1/2/2024 Permit Finaled JUAN VALENZUELA