13755 N GLADSTONE AVE 91342

Certificate Information: 13755 N GLADSTONE AVE 91342

Application / Permit
22016-20000-20733
Plan Check / Job No.
B22VN10789
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan EXISTING ACCESSARY LIVING QUARTER TO ADU per GCS 65852.2(e)(1)(A) NO STRUCTURAL WORK, NO FOUNDATION WORK, ALL WORK DONE PER WFPP
Permit Issued
Issued on 10/20/2022
Issuing Office
Current Status
CofO Issued on 4/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/15/2022 APPLICANT
Assigned to Plan Check Engineer 7/18/2022 DANIEL SANJUAN
Corrections Issued 7/19/2022 DANIEL SANJUAN
Plan Check Approved 10/13/2022 KHUONG TRUONG
Issued 10/20/2022 APPLICANT
CofO in Progress 4/5/2023 ARAM AVEDISIAN
Permit Finaled 4/18/2023 MICHAEL SMITH
CofO Issued 4/18/2023 MICHAEL SMITH
Permit Finaled 4/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/20/2022 ROMAN GUTIERREZ
Sewer availability Cleared 7/20/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 7/22/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/17/2023 Approved ARAM AVEDISIAN
Final 3/17/2023 Corrections Issued ARAM AVEDISIAN
MERV13>=Final 3/17/2023 Approved ARAM AVEDISIAN
MERV13>=Rough 3/17/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 3/17/2023 Approved ARAM AVEDISIAN
Final 4/5/2023 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 4/5/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 4/5/2023 SGSOV Approved ARAM AVEDISIAN