10037-10039 N WISH AVE 91325
Certificate Information: 10037-10039 N WISH AVE 91325
- Application / Permit
- 22016-20000-20473
- Plan Check / Job No.
- B22VN10626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan EXISTING 2-CAR ATTACHED GARAGE CONVERSION TO ADU PER STATE LAW
- Permit Issued
- Issued on 3/29/2023
- Issuing Office
- Current Status
- Issued on 3/29/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2022 | SUNMIN LEE |
| Corrections Issued | 8/22/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 1/17/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 2/3/2023 | KHUONG TRUONG |
| Issued | 3/29/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 9/27/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 9/27/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/9/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/9/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/9/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 1/5/2023 | KIRK LINKLATER |
Contact Information
| Contractor | Esco Builders Inc; Lic. No.: 926293-B | , |
| Contractor | Esco Construction; Lic. No.: 926293-B | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 5/24/2023 | Partial Approval | JAVIER RAMOS JR |
| Sewer | 5/24/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/17/2023 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 7/17/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 7/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/17/2023 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 8/3/2023 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 8/3/2023 | Approved | MATTHEW NELSON |
| Drywall Nailing | 8/15/2023 | Partial Inspection | JAVIER RAMOS JR |
| Green Building Rough | 8/15/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/15/2023 | Partial Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/7/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Shower Pan | 9/7/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/21/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/27/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/13/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 2/13/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/13/2024 | Approved | JAVIER RAMOS JR |
| Final | 2/13/2024 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 2/13/2024 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Final | 2/13/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/13/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/13/2024 | Approved | JAVIER RAMOS JR |