20157 W VENTURA BLVD 91364

Certificate Information: 20157 W VENTURA BLVD 91364

Application / Permit
22016-20000-20410
Plan Check / Job No.
B22VN10589
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
ePLAN. PROJECT HOMEKEY. TENANT IMPROVEMENT TO (E) HOTEL.
Permit Issued
Issued on 10/20/2022
Issuing Office
Current Status
Permit Finaled on 6/28/2023

Permit Application Status History

Submitted 7/18/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 KEVIN MORALES
Corrections Issued 7/25/2022 KEVIN MORALES
Quality Review Completed 7/28/2022 EUGENE BARBEAU
Applicant returned to address corrections 8/15/2022 KEVIN MORALES
Applicant returned to address corrections 9/8/2022 KEVIN MORALES
Applicant returned to address corrections 10/5/2022 KEVIN MORALES
Applicant returned to address corrections 10/13/2022 KEVIN MORALES
Plan Check Approved 10/20/2022 KEVIN MORALES
Issued 10/20/2022 APPLICANT
Permit Finaled 6/27/2023 BRIAN KELLY

Permit Application Clearance Information

Green Code Cleared 7/30/2022 DONALD CRICHLOW
Fire Marshal Fire Life Safety Cleared 9/12/2022 MENOA AGHAJANI
DAS Clearance Cleared 10/11/2022 Hernan Arreola

Contact Information

Architect Kadribegovic,, Nerin; Lic. No.: NA32104       ,
Contractor Ford E C Inc; Lic. No.: 396212-B       ,

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/25/2022 Partial Approval JEFFREY DURAN
Footing/Foundation/Slab 11/8/2022 Not Ready for Inspection DANIEL VARNUM
Footing/Foundation/Slab 11/28/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 1/6/2023 Not Ready for Inspection BRIAN KELLY
Drywall Nailing 1/10/2023 Approved BRIAN KELLY
Interior/Exterior Lathing 3/15/2023 Partial Approval BRIAN KELLY
Final 4/13/2023 Not Ready for Inspection BRIAN KELLY
Green Building Final 4/13/2023 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 4/13/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 4/13/2023 Not Ready for Inspection BRIAN KELLY
Deputy Reinf. Concrete 4/14/2023 Conditional Approval BRIAN KELLY
Final 5/11/2023 Corrections Issued BRIAN KELLY
Green Building Final 5/11/2023 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 5/11/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 5/11/2023 Not Ready for Inspection BRIAN KELLY
Final 6/13/2023 Not Ready for Inspection BRIAN KELLY
Green Building Final 6/13/2023 Not Ready for Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 6/13/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 6/13/2023 Not Ready for Inspection BRIAN KELLY
Final 6/27/2023 Permit Finaled BRIAN KELLY
Green Building Final 6/27/2023 Approved BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 6/27/2023 SGSOV Approved BRIAN KELLY
Smoke Detectors 6/27/2023 Approved BRIAN KELLY