1858 S BROCKTON AVE 90025

Certificate Information: 1858 S BROCKTON AVE 90025

Application / Permit
22016-20000-20387
Plan Check / Job No.
B22VN09101
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF (E) GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) FOR 7'-8" X 20'-2" PORTION OF (E) 18'-2" X 20' -2" GARAGE, 1 CAR PARKING TO REMAIN ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/11/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 10/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 7/11/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 7/18/2022 OMID HEDAYAT
Building Plans Picked Up 7/19/2022 APPLICANT
Applicant returned to address corrections 8/15/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 9/15/2022 SEWADA ZADOORAN MILAGARDI
Issued 1/11/2023 APPLICANT
CofO in Progress 10/9/2024 KIRK SANDERS
CofO Issued 10/22/2024 RICHARD STEINBACH
Permit Finaled 10/22/2024 RICHARD STEINBACH

Permit Application Clearance Information

Sewer availability Cleared 7/20/2022 ANTHONY MAINEZ
Specific Plan Cleared 7/21/2022 CONNIE CHAUV
Eng Process Fee Ord 176,300 Cleared 7/27/2022 ANTHONY MAINEZ
Address approval Cleared 9/12/2022 VLADIMIR ARUTYUNYAN
Specific Plan Cleared 9/14/2022 EDUARDO HERMOSO

Contact Information

Architect Hsu,, Peggy P; Lic. No.: C32998 3708 BEVERLY RIDGE DR.      SHERMAN OAKS, CA 91423
Contractor Gramajo'S Custom Homes; Lic. No.: 753312-B 11520 JEFFERSON BLVD STE 222      CULVER CITY, CA 90230
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/5/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 4/10/2023 Not Ready for Inspection JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 1/5/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 1/5/2024 Not Ready for Inspection BEN MOLSTAD
Sewer 1/5/2024 Not Ready for Inspection BEN MOLSTAD
Shower Pan 1/5/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 1/9/2024 Not Ready for Inspection BEN MOLSTAD
PLUMBING-Rough 1/9/2024 Not Ready for Inspection BEN MOLSTAD
Sewer 1/9/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Rough 1/16/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 1/16/2024 Approved BEN MOLSTAD
PLUMBING-Rough 1/16/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 1/24/2024 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 1/24/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 1/24/2024 Not Ready for Inspection BEN MOLSTAD
HVAC-Rough 1/30/2024 Corrections Issued BEN MOLSTAD
Special/Order Compliance 1/30/2024 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 2/8/2024 Approved JESUS PINEDA
Green Building Rough 2/8/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 2/8/2024 Approved JESUS PINEDA
Sewer 3/28/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 4/4/2024 Partial Approval ASHLEY THOMPSON
Insulation 5/7/2024 Approved ASHLEY THOMPSON
BUILDING-Rough-Frame 5/20/2024 Approved KIRK SANDERS
Drywall Nailing 5/20/2024 Approved KIRK SANDERS
Green Building Rough 5/20/2024 Approved KIRK SANDERS
ELECTRICAL-Final 7/22/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Final 7/22/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Final 7/22/2024 Not Ready for Inspection KIRK SANDERS
Service/Power Release 7/22/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 7/24/2024 Corrections Issued KIRK SANDERS
HVAC-Final 7/24/2024 Corrections Issued KIRK SANDERS
PLUMBING-Final 7/24/2024 Corrections Issued KIRK SANDERS
Service/Power Release 7/24/2024 Not Ready for Inspection KIRK SANDERS
HVAC-Final 7/30/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 9/12/2024 Corrections Issued KIRK SANDERS
Final 9/12/2024 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 9/12/2024 Approved KIRK SANDERS
Green Building Final 9/12/2024 Approved KIRK SANDERS
HVAC-Final 9/12/2024 Corrections Issued KIRK SANDERS
PLUMBING-Final 9/12/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/12/2024 SGSOV Approved KIRK SANDERS
Smoke Detectors 9/12/2024 Approved KIRK SANDERS
ELECTRICAL-Final 9/18/2024 Corrections Issued KIRK SANDERS
Final 9/18/2024 Partial Approval KIRK SANDERS
ELECTRICAL-Final 10/8/2024 Approved KIRK SANDERS
Final 10/8/2024 OK to Issue CofO KIRK SANDERS
Service/Power Release 10/8/2024 Approved KIRK SANDERS