6469-6471 N LONGRIDGE AVE 91401
Certificate Information: 6469-6471 N LONGRIDGE AVE 91401
- Application / Permit
- 22016-20000-20008
- Plan Check / Job No.
- B22VN10402
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) GARAGE TO JUNIOR ACCESSORY DWELLING PER GCS 65852.2(e)(1)(A) and 65852.22 UNIT ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 8/4/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/10/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 8/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 8/23/2022 | APPLICANT |
| Plan Check Approved | 1/23/2023 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/23/2023 | APPLICANT |
| CofO in Progress | 1/16/2024 | JOSE AVILA |
| Permit Finaled | 3/15/2024 | RUBEN SALAS |
| CofO Issued | 3/15/2024 | RUBEN SALAS |
| Permit Finaled | 3/15/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 10/14/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 1/20/2023 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 1/20/2023 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 1/20/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/27/2023 | Corrections Issued | KIRK SANDERS |
| Underground Mechanical | 7/27/2023 | Approved | KIRK SANDERS |
| Deputy Drilled-In Anchors | 8/3/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/4/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 8/16/2023 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 8/16/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 8/16/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 8/16/2023 | Approved | KIRK SANDERS |
| Insulation | 8/22/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Wood Frame | 8/22/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 8/24/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Wood Frame | 8/24/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 9/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2023 | Corrections Issued | KIRK SANDERS |
| Insulation | 9/14/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 9/14/2023 | Approved | KIRK SANDERS |
| Drywall Nailing | 9/25/2023 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 9/25/2023 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/25/2023 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 9/25/2023 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/27/2023 | Approved | KIRK SANDERS |
| Final | 11/27/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 11/27/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 11/27/2023 | SGSOV Not Ready | KIRK SANDERS |
| Smoke Detectors | 11/27/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 12/7/2023 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 12/7/2023 | Corrections Issued | JOSE AVILA |
| Final | 12/18/2023 | Corrections Issued | JOSE AVILA |
| Smoke Detectors | 12/18/2023 | Approved | JOSE AVILA |
| Final | 1/8/2024 | OK to Issue CofO | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/8/2024 | SGSOV Approved | JOSE AVILA |