734 N MCCADDEN PL 90038

Certificate Information: 734 N MCCADDEN PL 90038

Application / Permit
22016-20000-19939
Plan Check / Job No.
B22VN10359
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED 20'-0" X 20'-0" GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - ALL WORK PER ENGINEER
Permit Issued
Issued on 11/17/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2022 APPLICANT
Assigned to Plan Check Engineer 7/9/2022 DANIEL ABRAMYAN
Corrections Issued 7/9/2022 DANIEL ABRAMYAN
Building Plans Picked Up 7/12/2022 APPLICANT
Plan Check Approved 7/29/2022 ANGELICA MARTINEZ
Issued 11/17/2022 APPLICANT
CofO in Progress 11/17/2023 JOAQUIN GREENOUGH
Permit Finaled 11/21/2023 DEROLD HAUFF
CofO Issued 11/21/2023 DEROLD HAUFF
Permit Finaled 11/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/18/2022 AMAAN MALIK
Sewer availability Cleared 7/18/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 7/19/2022 AMAAN MALIK
Construction near power lines Cleared 7/22/2022 RIDWAN HARDY
Construction within easement Cleared 7/22/2022 RIDWAN HARDY

Contact Information

Contractor Sulgatti General Contractors Inc; Lic. No.: 912572-B 2341 FLINTRIDGE DRIVE      GLENDALE, CA 91206
Engineer Phillips,, Craig; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 2/1/2023 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Rough 2/1/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 2/8/2023 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 3/14/2023 Corrections Issued BRIAN SULLIVAN
Underground Mechanical 3/24/2023 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 3/30/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/3/2023 Approved JOAQUIN GREENOUGH
Pre-Inspection 5/12/2023 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 6/29/2023 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 7/17/2023 Partial Inspection BRIAN SULLIVAN
Deputy Drilled-In Anchors 7/26/2023 Conditional Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/26/2023 Partial Approval STUART CHAPMAN
Insulation 7/26/2023 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 8/9/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/9/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 8/9/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 8/9/2023 Approved JOAQUIN GREENOUGH
Insulation 8/17/2023 Partial Approval JOAQUIN GREENOUGH
Interior/Exterior Lathing 8/22/2023 Partial Approval BRIAN SULLIVAN
Shower Pan 8/22/2023 Approved BRIAN SULLIVAN
Drywall Nailing 9/1/2023 Approved BRIAN SULLIVAN
Insulation 9/1/2023 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 9/1/2023 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 10/11/2023 Approved JOAQUIN GREENOUGH
Final 10/11/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 10/11/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Green Building Rough 10/11/2023 Approved JOAQUIN GREENOUGH
METHANE-Final 10/11/2023 Approved JOAQUIN GREENOUGH
METHANE-Rough 10/11/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Smoke Detectors 10/11/2023 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Final 10/31/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 10/31/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 10/31/2023 SGSOV Approved JOAQUIN GREENOUGH
Smoke Detectors 10/31/2023 Approved JOAQUIN GREENOUGH
Final 11/14/2023 OK to Issue CofO JOAQUIN GREENOUGH