22136-22138 W GRESHAM ST 91304

Certificate Information: 22136-22138 W GRESHAM ST 91304

Application / Permit
22016-20000-19867
Plan Check / Job No.
B22VN10318
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Convert existing garage to new ADU (600 Sq. Ft.)
Permit Issued
Issued on 7/25/2022
Issuing Office
Current Status
CofO Issued on 7/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/5/2022 APPLICANT
Assigned to Plan Check Engineer 7/10/2022 DANIEL YIP
Corrections Issued 7/10/2022 DANIEL YIP
Plan Check Approved 7/22/2022 DANIEL YIP
Issued 7/25/2022 APPLICANT
CofO in Progress 6/2/2023 CHRIS CHRISTENSEN
Permit Finaled 7/31/2023 JOHN JANSON
CofO Issued 7/31/2023 JOHN JANSON
Permit Finaled 7/31/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/13/2022 CHRIS CHAHBAZ
Sewer availability Cleared 7/13/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 7/14/2022 CHRIS CHAHBAZ
Grading Pre-Inspection Cleared 7/18/2022 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/23/2023 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 2/27/2023 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/27/2023 Conditional Approval CHRIS CHRISTENSEN
Pre-Inspection 2/27/2023 Approved CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 2/28/2023 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 2/28/2023 Approved CHRIS CHRISTENSEN
Pre-Inspection 2/28/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/13/2023 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 3/13/2023 Approved CHRIS CHRISTENSEN
Wood Frame 3/13/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/17/2023 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/17/2023 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 3/17/2023 Conditional Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 3/17/2023 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 3/22/2023 Approved CHRIS CHRISTENSEN
Shower Pan 3/22/2023 Approved CHRIS CHRISTENSEN
Wood Frame 3/22/2023 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 4/3/2023 Approved CHRIS CHRISTENSEN
Green Building Rough 4/3/2023 Approved CHRIS CHRISTENSEN
Insulation 4/3/2023 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 4/3/2023 Approved CHRIS CHRISTENSEN
Wood Frame 4/3/2023 Approved CHRIS CHRISTENSEN
Drywall Nailing 4/13/2023 Approved CHRIS CHRISTENSEN
Final 5/23/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 5/23/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 6/1/2023 Approved CHRIS CHRISTENSEN
Final 6/1/2023 OK to Issue CofO CHRIS CHRISTENSEN