211-213 W 82ND ST 90003

Certificate Information: 211-213 W 82ND ST 90003

Application / Permit
22016-20000-19756
Plan Check / Job No.
B22VN10271
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan NEW 25' X 94' TWO STORY DUPLEX WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 2/7/2023
Issuing Office
Current Status
CofO Issued on 10/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/19/2022 APPLICANT
Assigned to Plan Check Engineer 7/22/2022 SELLA BENYAMIN
Corrections Issued 7/24/2022 SELLA BENYAMIN
Quality Review Completed 8/16/2022 JOHN FRANCIA
Plan Check Approved 10/7/2022 SELLA BENYAMIN
Issued 2/7/2023 APPLICANT
CofO in Progress 9/27/2023 MICHAEL LEWIS
Permit Finaled 10/4/2023 DEROLD HAUFF
CofO Issued 10/4/2023 DEROLD HAUFF
Permit Finaled 10/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/25/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 8/29/2022 STEVE MELGAR
Sewer availability Cleared 8/29/2022 STEVE MELGAR
Low Impact Development Cleared 9/20/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 9/22/2022 STEVE MELGAR
Hydrant and Access approval Cleared 10/3/2022 MATTHEW CRAIG

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH,, CA 90742
Engineer Madero,, Fidencio; Lic. No.: NA81695       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/19/2023 Approved LILIANA PORTILLO
Underground Mechanical 5/9/2023 Approved MICHAEL LEWIS
Wood Frame 5/9/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/10/2023 Partial Approval MICHAEL LEWIS
Insulation 5/10/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/16/2023 Partial Approval MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/30/2023 Approved MICHAEL LEWIS
HVAC-Rough 6/22/2023 Conditional Approval ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/22/2023 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 6/23/2023 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 6/23/2023 Approved MICHAEL LEWIS
Green Building Rough 6/23/2023 Approved MICHAEL LEWIS
PLUMBING-Rough 6/23/2023 Approved MICHAEL LEWIS
Insulation 6/27/2023 Approved MICHAEL LEWIS
Drywall Nailing 7/13/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/13/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 8/31/2023 Partial Approval MICHAEL LEWIS
HVAC-Final 9/25/2023 Approved MICHAEL LEWIS
PLUMBING-Final 9/25/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/26/2023 Approved MICHAEL LEWIS
ELECTRICAL-Final 9/26/2023 Approved MICHAEL LEWIS
Final 9/26/2023 OK to Issue CofO MICHAEL LEWIS
Green Building Final 9/26/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved MICHAEL LEWIS
Service/Power Release 9/26/2023 Approved MICHAEL LEWIS
Smoke Detectors 9/26/2023 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 9/26/2023 Approved MICHAEL LEWIS
Service/Power Release 9/27/2023 Approved MICHAEL LEWIS