15952 W SEPTO ST 91343

Certificate Information: 15952 W SEPTO ST 91343

Application / Permit
22016-20000-19531
Plan Check / Job No.
B22VN10176
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c)-(d). ALL WORK PER WFPP.
Permit Issued
Issued on 7/22/2022
Issuing Office
Current Status
CofO Issued on 9/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/30/2022 APPLICANT
Assigned to Plan Check Engineer 7/1/2022 SERGIO MUNIZ
Corrections Issued 7/3/2022 SERGIO MUNIZ
Plan Check Approved 7/22/2022 SERGIO MUNIZ
Issued 7/22/2022 APPLICANT
Building Plans Picked Up 7/22/2022 APPLICANT
CofO in Progress 8/15/2023 JAVIER RAMOS JR
CofO Issued 9/19/2023 RUBEN SALAS
Permit Finaled 9/19/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/6/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/6/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/8/2022 DAGOVERTO GUERRERO
Grading Pre-Inspection Cleared 7/11/2022 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/25/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 9/12/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 9/19/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 10/13/2022 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 10/13/2022 Corrections Issued JAVIER RAMOS JR
Green Building Rough 10/13/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 10/13/2022 Approved JAVIER RAMOS JR
Wood Frame 10/13/2022 Partial Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 11/4/2022 Approved JAVIER RAMOS JR
Green Building Rough 11/4/2022 Approved JAVIER RAMOS JR
Insulation 11/4/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/4/2022 Partial Approval JAVIER RAMOS JR
Wood Frame 11/4/2022 Approved JAVIER RAMOS JR
Drywall Nailing 12/7/2022 Approved ROBERT GOLD
ELECTRICAL-Rough 12/15/2022 Approved JAVIER RAMOS JR
HVAC-Rough 12/15/2022 Approved JAVIER RAMOS JR
Sewer 12/15/2022 Approved JAVIER RAMOS JR
Shower Pan 12/15/2022 Approved JAVIER RAMOS JR
Underground Mechanical 12/15/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/22/2022 Approved JAVIER RAMOS JR
Final 7/11/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 7/11/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 7/11/2023 Approved JAVIER RAMOS JR
Final 8/14/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 8/14/2023 Approved JAVIER RAMOS JR