3908 N LOWELL AVE 90032

Certificate Information: 3908 N LOWELL AVE 90032

Application / Permit
22016-20000-19528
Plan Check / Job No.
B22VN10174
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WORK PER WFPP.
Permit Issued
Issued on 10/11/2022
Issuing Office
Current Status
CofO Issued on 9/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/14/2022 APPLICANT
Assigned to Plan Check Engineer 7/15/2022 SERGIO MUNIZ
Corrections Issued 7/16/2022 SERGIO MUNIZ
Building Plans Picked Up 8/4/2022 APPLICANT
Applicant returned to address corrections 9/7/2022 RAMA DABADGE
Applicant returned to address corrections 9/29/2022 JESSE ARELLANO
Applicant returned to address corrections 10/4/2022 ROSENDO MEDINA
Plan Check Approved 10/11/2022 ROSENDO MEDINA
Issued 10/11/2022 APPLICANT
CofO in Progress 9/1/2023 AMY COLIN
CofO Issued 9/12/2023 RONALD MYRICK
Permit Finaled 9/12/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 8/18/2022 TREVOR QUAN
Sewer availability Cleared 8/18/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/22/2022 TREVOR QUAN
Grading Pre-Inspection Cleared 8/25/2022 KIRK LINKLATER
Miscellaneous Cleared 9/28/2022 DANG NGUYEN
Construction near power lines Cleared 10/7/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/14/2022 Partial Inspection AMY COLIN
Excavation/Setback/Form/Re-Bar 11/21/2022 Corrections Issued AMY COLIN
Footing/Foundation/Slab 11/21/2022 Partial Approval AMY COLIN
Reinforced Concrete Frame 11/21/2022 Partial Approval AMY COLIN
Footing/Foundation/Slab 11/22/2022 No Access for Inspection AMY COLIN
Reinforced Concrete Frame 11/22/2022 No Access for Inspection AMY COLIN
ELECTRICAL-Rough 1/4/2023 Approved AMY COLIN
PLUMBING-Rough 1/4/2023 Approved AMY COLIN
BUILDING-Rough-Frame 1/18/2023 Partial Approval AMY COLIN
HVAC-Rough 1/18/2023 Approved AMY COLIN
Insulation 1/31/2023 Approved RUBEN SALAS
BUILDING-Rough-Frame 2/7/2023 Approved RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved RUBEN SALAS
Green Building Rough 2/7/2023 Approved RUBEN SALAS
Drywall Nailing 2/16/2023 Approved AMY COLIN
Shower Pan 2/16/2023 Approved AMY COLIN
Interior/Exterior Lathing 2/21/2023 Approved AMY COLIN
Interior/Exterior Lathing 2/23/2023 Partial Inspection RUBEN SALAS
Sewer 3/23/2023 Not Ready for Inspection AMY COLIN
Sewer 3/25/2023 Approved AMY COLIN
ELECTRICAL-Rough 4/18/2023 Corrections Issued RUBEN SALAS
ELECTRICAL-Final 5/10/2023 Corrections Issued AMY COLIN
Final 5/10/2023 Corrections Issued AMY COLIN
Green Building Final 5/10/2023 Approved AMY COLIN
HVAC-Final 5/10/2023 Approved AMY COLIN
PLUMBING-Final 5/10/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 5/10/2023 SGSOV Not Ready AMY COLIN
Service/Power Release 5/10/2023 Not Ready for Inspection AMY COLIN
Smoke Detectors 5/10/2023 Approved AMY COLIN
ELECTRICAL-Final 8/30/2023 Approved AMY COLIN
Final 8/30/2023 OK to Issue CofO AMY COLIN
SGSOV-Seismic Gas S/O Valve 8/30/2023 SGSOV Approved AMY COLIN
Service/Power Release 8/30/2023 Approved AMY COLIN