18324 W CITRONIA ST 91325
Certificate Information: 18324 W CITRONIA ST 91325
- Application / Permit
- 22016-20000-19503
- Plan Check / Job No.
- B22VN10162
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT FIRST FLOOR OF (E) 30'x42' DET. GARAGE TO NEW ACCESSORY DWELLING UNIT (PER CA Govt. Code 65852.2(e)(1)(A)) AND REMOVE THE (E) 2ND FLOOR; NFPA-13D THRU-OUT
- Permit Issued
- Issued on 5/26/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/23/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/29/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/14/2022 | SEAN SHAHMIRI |
| Corrections Issued | 7/18/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 7/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/25/2022 | APPLICANT |
| Applicant returned to address corrections | 12/15/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 12/15/2022 | SEAN SHAHMIRI |
| Issued | 5/26/2023 | APPLICANT |
| CofO in Progress | 4/19/2024 | KRISTEN BEVERIDGE |
| Permit Finaled | 4/23/2024 | JOHN JANSON |
| CofO Issued | 4/23/2024 | JOHN JANSON |
| Permit Finaled | 4/23/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/28/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 8/16/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 8/17/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 8/17/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2022 | JOSE DUARTE-DIAZ |
| Hydrant and Access approval | Cleared | 9/16/2022 | LAVEON RIDER |
| Construction within easement | Cleared | 10/14/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Van, Elden, Alexander Craig; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/1/2023 | Partial Approval | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 6/14/2023 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/16/2023 | Approved | DAVID SCANTLIN |
| Deputy Drilled-In Anchors | 8/23/2023 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 8/23/2023 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 8/25/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/6/2023 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/6/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 9/6/2023 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/6/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/12/2023 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/12/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 9/12/2023 | Not Ready for Inspection | JOHN KIDWELL |
| HVAC-Rough | 9/12/2023 | Approved | JOHN KIDWELL |
| Shower Pan | 9/12/2023 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 9/26/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Rough | 9/26/2023 | Not Ready for Inspection | JOHN KIDWELL |
| Shower Pan | 9/26/2023 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 10/6/2023 | Approved | JOHN KIDWELL |
| Green Building Rough | 10/6/2023 | Approved | JOHN KIDWELL |
| Insulation | 10/6/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 10/6/2023 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 10/12/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 11/15/2023 | Partial Approval | JOHN KIDWELL |
| Sewer | 1/2/2024 | Corrections Issued | JEFFREY PARD |
| Pre-Inspection | 1/4/2024 | Approved | DAVID SCANTLIN |
| Sewer | 1/4/2024 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 3/5/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Final | 3/5/2024 | Approved | DAVID SCANTLIN |
| Final | 3/15/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Green Building Final | 3/15/2024 | Approved | KRISTEN CAUSEY |
| SGSOV-Seismic Gas S/O Valve | 3/15/2024 | SGSOV Not Required | KRISTEN CAUSEY |
| Smoke Detectors | 3/15/2024 | Approved | KRISTEN CAUSEY |
| Final | 3/21/2024 | Partial Inspection | KRISTEN CAUSEY |
| Final | 3/27/2024 | Not Ready for Inspection | KRISTEN CAUSEY |
| Final | 4/19/2024 | OK to Issue CofO | KRISTEN CAUSEY |
| Service/Power Release | 4/19/2024 | Approved | KRISTEN CAUSEY |