22235 W COHASSET ST 91303

Certificate Information: 22235 W COHASSET ST 91303

Application / Permit
22016-20000-19324
Plan Check / Job No.
B22VN10064
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO ADU W/ ADDITION- 2 BEDROOM 2 BATH
Permit Issued
Issued on 7/15/2024
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 7/8/2022 JOE VO
Corrections Issued 7/8/2022 JOE VO
Plan Check Approved 7/11/2024 JOE VO
Issued 7/15/2024 APPLICANT
CofO in Progress 7/18/2025 CHRIS CHRISTENSEN
CofO Issued 7/31/2025 DANIEL ORRANTE
Permit Finaled 7/31/2025 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/13/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 7/13/2022 MEGAN GODINEZ
Construction near power lines Cleared 7/22/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 7/3/2024 CARLOS AGUILERA
Sewer availability Cleared 7/3/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/20/2024 Conditional Approval JEFFREY HARTLINE
Sewer 9/23/2024 Partial Approval CHRIS CHRISTENSEN
Underground Mechanical 9/23/2024 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/25/2024 Corrections Issued CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 9/30/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 10/2/2024 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 10/18/2024 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 10/18/2024 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/18/2024 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/30/2024 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/30/2024 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 10/30/2024 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 11/5/2024 Approved CHRIS CHRISTENSEN
Green Building Rough 11/5/2024 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/5/2024 Partial Approval CHRIS CHRISTENSEN
Insulation 11/7/2024 Corrections Issued CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/7/2024 Partial Approval CHRIS CHRISTENSEN
Insulation 11/12/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 11/14/2024 Approved CHRIS CHRISTENSEN
Drywall Nailing 12/24/2024 Approved TROY SANDERS
Shower Pan 12/24/2024 Approved TROY SANDERS
Interior/Exterior Lathing 12/30/2024 Approved CHRIS CHRISTENSEN
Final 4/23/2025 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 4/23/2025 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 4/23/2025 Approved CHRIS CHRISTENSEN
Final 5/29/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 5/29/2025 Approved CHRIS CHRISTENSEN
Final 7/10/2025 Not Ready for Inspection JEFFREY HARTLINE
ELECTRICAL-Final 7/17/2025 Approved CHRIS CHRISTENSEN
Final 7/17/2025 OK to Issue CofO CHRIS CHRISTENSEN