14383 W AZTEC ST 91342

Certificate Information: 14383 W AZTEC ST 91342

Application / Permit
22016-20000-19301
Plan Check / Job No.
B22VN10044
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT (489 SQ FT) PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/28/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 JEROME MAGAT PALMA
Corrections Issued 7/2/2022 JEROME MAGAT PALMA
Building Plans Picked Up 7/8/2022 APPLICANT
Plan Check Approved 11/14/2022 ANGELICA MARTINEZ
Issued 11/28/2022 APPLICANT
CofO in Progress 12/26/2023 MATTHEW NELSON
Permit Finaled 1/3/2024 RUBEN SALAS
Permit Finaled 1/3/2024 RUBEN SALAS
CofO Issued 1/3/2024 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 8/24/2022 RIDWAN HARDY
Address approval Cleared 11/7/2022 CHRIS CHAHBAZ
Sewer availability Cleared 11/7/2022 CHRIS CHAHBAZ
Eng Process Fee Ord 176,300 Cleared 11/8/2022 CHRIS CHAHBAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/31/2023 Partial Approval JENNIFER RABUCHIN
Sewer 3/31/2023 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 4/28/2023 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 5/5/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 5/5/2023 Approved JENNIFER RABUCHIN
Structural Steel Frame 5/5/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/12/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/12/2023 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 6/12/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/12/2023 Corrections Issued JENNIFER RABUCHIN
Wood Frame 6/12/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/14/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 7/14/2023 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 7/14/2023 Approved JENNIFER RABUCHIN
Green Building Rough 7/14/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 7/14/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 7/14/2023 Approved JENNIFER RABUCHIN
Wood Frame 7/14/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/7/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 8/7/2023 Partial Approval JENNIFER RABUCHIN
Insulation 8/7/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 8/10/2023 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 8/25/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 8/29/2023 Approved JENNIFER RABUCHIN
Special/Order Compliance 8/29/2023 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 10/19/2023 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/18/2023 Partial Inspection JAVIER RAMOS JR
Final 12/18/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/18/2023 Not Ready for Inspection JAVIER RAMOS JR
Insulation 12/18/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/18/2023 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 12/18/2023 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 12/22/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/26/2023 Approved MATTHEW NELSON
Final 12/26/2023 OK to Issue CofO MATTHEW NELSON
Green Building Final 12/26/2023 Approved MATTHEW NELSON
Smoke Detectors 12/26/2023 Approved MATTHEW NELSON