19522 W VENTURA BLVD 91356
Certificate Information: 19522 W VENTURA BLVD 91356
- Application / Permit
- 22016-20000-19118
- Plan Check / Job No.
- B22VN09887
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ePLAN. CHANGE OF USE FROM OFFICE TO RESTAURANT.
- Permit Issued
- Issued on 3/20/2023
- Issuing Office
- Current Status
- CofO Issued on 6/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2022 | KEVIN MORALES |
| Corrections Issued | 7/4/2022 | KEVIN MORALES |
| Applicant returned to address corrections | 12/7/2022 | KEVIN MORALES |
| Plan Check Approved | 3/2/2023 | KEVIN MORALES |
| Issued | 3/20/2023 | APPLICANT |
| CofO in Progress | 6/11/2024 | BRIAN KELLY |
| Permit Finaled | 6/13/2024 | JEFFREY DURAN |
| CofO Issued | 6/13/2024 | JEFFREY DURAN |
| Permit Finaled | 6/13/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| Food establishment approval | Cleared | 12/7/2022 | LACDHS APPROVED |
| Specific Plan | Cleared | 12/19/2022 | ADRINEH MELKONIAN |
| "D" conditions | Cleared | 12/21/2022 | JAZMIN ROQUE |
| ZA Case | Cleared | 1/11/2023 | OMAR GALICIA |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/26/2023 | CARLOS AGUILERA |
| Food Service Establishment | Cleared | 2/28/2023 | PAWAN VERMA |
Contact Information
| Contractor | Kasteler Construction Inc; Lic. No.: 1039992-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/14/2023 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 4/17/2023 | Partial Approval | BRIAN KELLY |
| Deputy Steel/Welding | 4/24/2023 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 4/25/2023 | Approved | BRIAN KELLY |
| Light Gage Steel Frame | 6/20/2023 | Partial Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 1/18/2024 | Conditional Approval | BRIAN KELLY |
| Light Gage Steel Frame | 1/25/2024 | Partial Approval | BRIAN KELLY |
| Insulation | 1/26/2024 | Partial Approval | BRIAN KELLY |
| Special/Order Compliance | 1/26/2024 | Partial Approval | MELVIN GIRTON |
| Drywall Nailing | 1/29/2024 | Partial Approval | BRIAN KELLY |
| T-Bar Ceiling | 2/21/2024 | Partial Inspection | BRIAN KELLY |
| Final | 6/3/2024 | OK to Issue CofO | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/3/2024 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 6/3/2024 | Approved | BRIAN KELLY |
| Wood Frame | 6/3/2024 | Approved | BRIAN KELLY |