13730-13732 N MINDORA AVE 91342
Certificate Information: 13730-13732 N MINDORA AVE 91342
- Application / Permit
- 22016-20000-18900
- Plan Check / Job No.
- B22VN09780
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED 21'X 20'6" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP.
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/23/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | HAYATO TSUCHIYA |
| Corrections Issued | 6/25/2022 | HAYATO TSUCHIYA |
| Building Plans Picked Up | 7/27/2022 | APPLICANT |
| Applicant returned to address corrections | 7/28/2022 | GURUNATH NESARAJAH |
| Plan Check Approved | 8/9/2022 | ALEC MOUSAKHANIAN |
| Issued | 8/9/2022 | APPLICANT |
| CofO in Progress | 1/12/2023 | ARAM AVEDISIAN |
| Permit Finaled | 2/1/2023 | MICHAEL SMITH |
| CofO Issued | 2/1/2023 | MICHAEL SMITH |
| Permit Finaled | 2/1/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2022 | CHRIS CHAHBAZ |
| Sewer availability | Cleared | 6/29/2022 | CHRIS CHAHBAZ |
| Grading Pre-Inspection | Cleared | 7/27/2022 | HAYATO TSUCHIYA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/15/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 8/18/2022 | No Result Entered | KENNETH KUROWSKI |
| Footing/Foundation/Slab | 8/19/2022 | Approved | ARAM AVEDISIAN |
| Sewer | 8/19/2022 | Approved | ARAM AVEDISIAN |
| Wood Frame | 8/29/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/15/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/15/2022 | Conditional Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/15/2022 | Approved | ARAM AVEDISIAN |
| Shower Pan | 9/19/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/23/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 9/23/2022 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/23/2022 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 9/27/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 9/27/2022 | Partial Approval | ARAM AVEDISIAN |
| Special/Order Compliance | 10/5/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/9/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/18/2022 | Partial Approval | ARAM AVEDISIAN |
| HVAC-Final | 11/18/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 12/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 12/20/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 12/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 12/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 12/20/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 12/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 1/12/2023 | Approved | ARAM AVEDISIAN |
| Final | 1/12/2023 | OK to Issue CofO | ARAM AVEDISIAN |
| Green Building Final | 1/12/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 1/12/2023 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 1/12/2023 | Approved | ARAM AVEDISIAN |