13905 W RAYEN ST 91331
Certificate Information: 13905 W RAYEN ST 91331
- Application / Permit
- 22016-20000-18798
- Plan Check / Job No.
- B22VN09712
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE INTO A (N) DETACHED 20'-0" x 18'-0" ACCESSORY DWELLING UNIT TO COMPLY WITH GCS65852.2(e)(1)(A) PER WFPP
- Permit Issued
- Issued on 11/9/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/20/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/15/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 7/16/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Applicant returned to address corrections | 10/25/2022 | MIROOSH KHACHATOORIAN |
| Issued | 11/9/2022 | APPLICANT |
| CofO in Progress | 7/11/2023 | GREGG CUMMINGS |
| Permit Finaled | 7/20/2023 | MICHAEL SMITH |
| Permit Finaled | 7/20/2023 | MICHAEL SMITH |
| CofO Issued | 7/20/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 9/14/2022 | DAGOVERTO GUERRERO |
| Construction near power lines | Cleared | 10/16/2022 | PATRICK MAGALLANES |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | 13302 FILMORE ST PACOIMA, CA 91331 |
| Engineer | Vasquez,, Mario A; Lic. No.: C89006 | 1942 SPANISH BROOM DR PALMDALE, CA 93550 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/7/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 12/7/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/7/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/6/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/6/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 1/6/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 1/6/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/6/2023 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 1/17/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/17/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 1/17/2023 | Approved | GREGG CUMMINGS |
| Wood Frame | 1/17/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 1/20/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 1/20/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 1/20/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 1/25/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 1/25/2023 | Partial Approval | GREGG CUMMINGS |
| Drywall Nailing | 1/27/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 1/27/2023 | Approved | GREGG CUMMINGS |
| Final | 6/26/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 6/26/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 6/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 6/26/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/10/2023 | Approved | GREGG CUMMINGS |
| Final | 7/10/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 7/10/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 7/10/2023 | Approved | GREGG CUMMINGS |
| Pre-Inspection | 7/10/2023 | Approved | GREGG CUMMINGS |