21601 W VICTORY BLVD 91303
Certificate Information: 21601 W VICTORY BLVD 91303
- Application / Permit
- 22016-20000-18581
- Plan Check / Job No.
- B22VN09601
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan New Sales Floor Fixtures with Fixture Department Reflow Demo of existing car installation bay with wall infill, new sales floor finishes, electrical connects, lighting adjustments, HVAC, Sprinkler Head Adjustments as required, exterior customer facing lockers, expanded curbside pick up with employee only access door. Please see scope of work for more detail on plans. Will not be doing signage on this permit.
- Permit Issued
- Issued on 2/2/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/29/2025
Permit Application Status History
| Submitted | 7/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/28/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 8/15/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 8/15/2022 | GARO TELMI |
| Plan Check Approved | 12/16/2022 | ARSALAN SHABESTARI |
| Issued | 2/2/2023 | APPLICANT |
| Permit Finaled | 8/28/2025 | BRIAN KELLY |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/5/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 10/5/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/11/2022 | ROMAN GUTIERREZ |
| Specific Plan | Cleared | 10/11/2022 | SHIRLEY ZAMORA |
| Miscellaneous | Cleared | 10/12/2022 | KRISTINE JEGALIAN |
| Miscellaneous | Cleared | 10/12/2022 | KRISTINE JEGALIAN |
| Specific Plan | Cleared | 10/12/2022 | KRISTINE JEGALIAN |
| DAS Clearance | Cleared | 10/26/2022 | Hernan Arreola |
| Green Code | Cleared | 11/10/2022 | Hernan Arreola |
| Miscellaneous | Cleared | 11/22/2022 | MIGUEL GAMBOA |
Contact Information
| Architect | Menard,, Nathan D; Lic. No.: NA27019 | , |
| Contractor | Schimenti Construction Company Llc; Lic. No.: 1045549-B | 650 DANBURY ROAD RIDGEFIELD, CT 06877 |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 5/31/2023 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 6/6/2023 | Partial Approval | BRIAN KELLY |
| Insulation | 6/7/2023 | Partial Approval | BRIAN KELLY |
| Wood Frame | 6/8/2023 | Partial Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 6/9/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Grading | 6/9/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 6/9/2023 | Conditional Approval | BRIAN KELLY |
| Wood Frame | 6/12/2023 | Partial Inspection | BRIAN KELLY |
| Deputy Drilled-In Anchors | 6/13/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 6/13/2023 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 6/13/2023 | Partial Approval | BRIAN KELLY |
| Insulation | 6/13/2023 | Partial Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 6/14/2023 | Conditional Approval | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 6/14/2023 | Partial Approval | BRIAN KELLY |
| Insulation | 6/20/2023 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 6/20/2023 | Partial Approval | BRIAN KELLY |
| T-Bar Ceiling | 6/20/2023 | Partial Approval | BRIAN KELLY |
| Drywall Nailing | 6/22/2023 | Partial Approval | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Not Ready for Inspection | BRIAN KELLY |
| Masonry Wall/Backfill | 6/22/2023 | Not Ready for Inspection | BRIAN KELLY |
| Deputy Reinf. Masonry | 6/23/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 6/26/2023 | Conditional Approval | KENNETH ROBERTS |
| Excavation/Setback/Form/Re-Bar | 6/27/2023 | Partial Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 6/27/2023 | Partial Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 6/28/2023 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 7/1/2023 | Off-Hour Fees Due | |
| Drywall Nailing | 7/1/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 7/1/2023 | Off-Hour Fees Due | |
| Green Building Rough | 7/1/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 7/1/2023 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 7/1/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 7/6/2023 | Partial Approval | BRIAN KELLY |
| Deputy Steel/Welding | 7/10/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 7/11/2023 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 7/11/2023 | Partial Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 7/12/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 7/12/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 7/13/2023 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 7/14/2023 | Partial Approval | BRIAN KELLY |
| Deputy Reinf. Concrete | 7/17/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Masonry | 7/17/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Reinf. Masonry | 7/19/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 7/19/2023 | Conditional Approval | BRIAN KELLY |
| Light Gage Steel Frame | 7/19/2023 | Partial Approval | BRIAN KELLY |
| Deputy Reinf. Masonry | 7/20/2023 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 7/21/2023 | Approved | BRIAN KELLY |
| Deputy Steel/Welding | 7/31/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 8/1/2023 | Conditional Approval | BRIAN KELLY |
| Wood Frame | 8/7/2023 | Partial Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 8/9/2023 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 8/28/2023 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 8/28/2023 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 8/29/2023 | Conditional Approval | STEVEN LEVITT |
| Light Gage Steel Frame | 8/31/2023 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 9/5/2023 | Partial Inspection | JEFFREY FULTON |
| Pre-Inspection | 9/15/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Reinf. Masonry | 9/26/2023 | Conditional Approval | JEFFREY DURAN |
| Excavation/Setback/Form/Re-Bar | 9/26/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 9/28/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Deputy Reinf. Masonry | 10/10/2023 | Conditional Approval | JEFFREY DURAN |
| Deputy Wood Construction | 4/26/2024 | Conditional Approval | BRIAN KELLY |
| Final | 11/27/2024 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 11/27/2024 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 11/27/2024 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 11/27/2024 | Not Ready for Inspection | BRIAN KELLY |
| Final | 8/28/2025 | Permit Finaled | BRIAN KELLY |
| Green Building Final | 8/28/2025 | Approved | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 8/28/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 8/28/2025 | Approved | BRIAN KELLY |