13864 W FOOTHILL BLVD 91342
Certificate Information: 13864 W FOOTHILL BLVD 91342
- Application / Permit
- 22016-20000-18454
- Plan Check / Job No.
- B22VN09566
- Group
- Building
- Type
- Grading
- Sub-Type
- Commercial
- Primary Use
- (60) Grading - Non-Hillside
- Work Description
- ePlan Site grading for new In-N-Out Burger restaurant. Total soil cut is 4,600 CU. YRDS, total compacted fill soil is 4,850 CU. YRDS, and estimated soil export is 250 CU. YRDS
- Permit Issued
- Issued on 5/24/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/8/2025
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | ZAW HAN |
| Corrections Issued | 7/11/2022 | ZAW HAN |
| Quality Review Completed | 7/12/2022 | CHAD DOI |
| Applicant returned to address corrections | 9/7/2022 | ZAW HAN |
| Applicant returned to address corrections | 10/21/2022 | ZAW HAN |
| Applicant returned to address corrections | 5/2/2023 | ZAW HAN |
| Plan Check Approved | 5/16/2023 | ZAW HAN |
| Issued | 5/24/2023 | APPLICANT |
| Permit Finaled | 7/7/2025 | CHARLES POWELL |
Permit Application Clearance Information
| APC | Cleared | 1/3/2023 | ANACANY HURTADO |
| Community Plan Implem. Overlay | Cleared | 1/3/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/3/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/3/2023 | ANACANY HURTADO |
| ZA Case | Cleared | 1/3/2023 | ANACANY HURTADO |
| Low Impact Development | Cleared | 4/22/2023 | ANDRES COVARRUBIAS |
Contact Information
| Contractor | In-N-Out Burgers; Lic. No.: 470763-B | , |
| Engineer | Kellogg,, James; Lic. No.: C65092 | 3169 SAINT ELMO AVE. CHATTANOOGA, TN 37408 |
| Engineer | Kellogg,, James; Lic. No.: GE2902 | 3169 SAINT ELMO AVE. CHATTANOOGA, TN 37408 |
| Engineer | Lamoureux,, Mark; Lic. No.: C38382 | 426 SAGE PLACE GLENDORA, CA 91740 |
| Engineer | Pelayo,, Jorge A; Lic. No.: C91269 | 1102 VINTAGE CIRCLE CORONA, CA 92881 |
Inspector Information
| BRIAN MILLER, (818) 374-4359 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Initial Grading | 5/31/2023 | Approved | MICHAEL TEMPLE |
| Bottom/Toe | 7/27/2023 | Corrections Issued | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 7/27/2023 | Conditional Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 7/31/2023 | Order to Comply Issued | ROBERT PINA |
| Bottom/Toe | 8/8/2023 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 8/21/2023 | Not Ready for Inspection | MICHAEL TEMPLE |
| Approved Compaction Report | 8/24/2023 | Approved | BRIAN MILLER |
| Drainage Devices/Catch Basin | 8/28/2023 | Partial Approval | MICHAEL TEMPLE |
| Drainage Devices/Catch Basin | 9/11/2023 | Partial Approval | MANUEL TEJADA |
| Sub-Drain | 9/11/2023 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 9/21/2023 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 1/4/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 1/16/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Rough | 1/16/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 1/30/2024 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Drainage Devices/Catch Basin | 2/25/2025 | Partial Approval | MANUEL TEJADA |
| Drainage Devices/Catch Basin | 3/10/2025 | Partial Approval | CHARLES POWELL |
| Bottom/Toe | 6/16/2025 | Approved | CHARLES POWELL |
| Final | 6/16/2025 | Corrections Issued | CHARLES POWELL |
| Rough | 6/16/2025 | Approved | CHARLES POWELL |
| Final | 7/7/2025 | Permit Finaled | CHARLES POWELL |