6613 N FORBES AVE 91406

Certificate Information: 6613 N FORBES AVE 91406

Application / Permit
22016-20000-18212
Plan Check / Job No.
B22VN09443
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE(18'-3"x20'-1"), 366 SQFT INTO ADU PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 11/18/2022
Issuing Office
Current Status
CofO Issued on 9/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 7/21/2022 PETER MOSESIAN
Corrections Issued 7/24/2022 PETER MOSESIAN
Quality Review Completed 7/29/2022 OMID HEDAYAT
Plan Check Approved 11/17/2022 PETER MOSESIAN
Issued 11/18/2022 APPLICANT
CofO in Progress 8/2/2023 RAUL OLAGI
Permit Finaled 9/6/2023 RUBEN SALAS
CofO Issued 9/6/2023 RUBEN SALAS
Permit Finaled 9/6/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/1/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 8/1/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 8/1/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 8/1/2022 JOSE DUARTE-DIAZ
ZI Cleared 8/2/2022 STEVEN WECHSLER
Construction near power lines Cleared 10/1/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 4/6/2023 Approved RAUL OLAGI
PLUMBING-Rough 4/6/2023 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 4/7/2023 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 4/24/2023 Not Ready for Inspection MATTHEW NELSON
HVAC-Rough 4/24/2023 Approved MATTHEW NELSON
PLUMBING-Rough 4/24/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 4/26/2023 Partial Approval RAUL OLAGI
ELECTRICAL-Rough 4/26/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/28/2023 Approved RAUL OLAGI
Insulation 4/28/2023 Approved RAUL OLAGI
Interior/Exterior Lathing 4/28/2023 Partial Approval RAUL OLAGI
Drywall Nailing 5/15/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 5/19/2023 Approved DAVID ANDERSON
Shower Pan 5/19/2023 Approved DAVID ANDERSON
Sewer 6/9/2023 Approved RAUL OLAGI
Underground Mechanical 6/9/2023 Partial Approval RAUL OLAGI
Final 8/2/2023 OK to Issue CofO RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/2/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 8/2/2023 Approved RAUL OLAGI