12298-12300 W JUDD ST 91342
Certificate Information: 12298-12300 W JUDD ST 91342
- Application / Permit
- 22016-20000-18209
- Plan Check / Job No.
- B22VN09441
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Convert existing attached garage into ADU per ordinance.
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Current Status
- Issued on 7/26/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2022 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/6/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 7/26/2022 | FARSHAD ALIMOHAMADI |
| Issued | 7/26/2022 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/21/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/21/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 7/25/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 7/25/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 7/25/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/27/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/6/2022 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 10/6/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 1/25/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/25/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/25/2023 | Corrections Issued | JUAN VALENZUELA |
| MERV13>=Rough | 1/25/2023 | Approved | JUAN VALENZUELA |
| METHANE-Rough | 1/25/2023 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 1/25/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Rough-Elec/Plmb/HVAC | 1/25/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 3/30/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 3/30/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 3/30/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 3/30/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 3/30/2023 | Approved | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 3/30/2023 | Partial Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/14/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/24/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/24/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 7/24/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 7/24/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 8/10/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/10/2023 | Corrections Issued | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 8/10/2023 | Partial Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/1/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2023 | Partial Approval | MICHEL ABAJAN |
| Rough-Elec/Plmb/HVAC | 9/1/2023 | Approved | MICHEL ABAJAN |
| Insulation | 8/28/2024 | Corrections Issued | LOUIS ESCOTO |
| Insulation | 9/4/2024 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 9/4/2024 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/4/2026 | Not Ready for Inspection | MICHEL ABAJAN |