19635 W VANOWEN ST 91335

Certificate Information: 19635 W VANOWEN ST 91335

Application / Permit
22016-20000-18207
Plan Check / Job No.
B22VN09437
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EXISTING REC. ROOM TO BE CONVERTED INTO ADU 371.66 S.F.
Permit Issued
Issued on 7/25/2022
Issuing Office
Current Status
CofO Issued on 7/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/16/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 JOE VO
Corrections Issued 7/11/2022 JOE VO
Plan Check Approved 7/20/2022 JOE VO
Issued 7/25/2022 APPLICANT
CofO in Progress 6/29/2023 JEFFREY BULL
CofO in Progress 7/13/2023 SEAN WIRCH
CofO in Progress 7/11/2024 JEFFREY BULL
Permit Finaled 7/11/2024 JOHN JANSON
CofO Issued 7/11/2024 JOHN JANSON
Permit Finaled 7/11/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 7/14/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 7/14/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/19/2022 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 7/25/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2022 Approved JEFFREY BULL
Deputy Drilled-In Anchors 9/21/2022 Approved JEFFREY BULL
PLUMBING-Rough 9/21/2022 Approved JEFFREY BULL
Wood Frame 9/21/2022 Approved JEFFREY BULL
HVAC-Rough 9/29/2022 Approved JEFFREY BULL
Footing/Foundation/Slab 3/8/2023 Approved JEFFREY BULL
PLUMBING-Rough 3/8/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 3/17/2023 Approved SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Approved SEAN HAUPT
Green Building Rough 3/17/2023 Approved SEAN HAUPT
Rough-Elec/Plmb/HVAC 3/17/2023 Approved SEAN HAUPT
Drywall Nailing 3/21/2023 Partial Approval DAVID SANDOVAL
Insulation 3/21/2023 Partial Inspection DAVID SANDOVAL
Interior/Exterior Lathing 3/21/2023 Corrections Issued DAVID SANDOVAL
Drywall Nailing 3/23/2023 Approved SEAN HAUPT
Final 4/4/2023 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/4/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 4/4/2023 Approved JEFFREY BULL
Special/Order Compliance 4/4/2023 Partial Inspection MORRIS JACKSON
Special/Order Compliance 7/14/2023 Corrections Issued JEFFREY BULL
Final 7/11/2024 OK to Issue CofO JEFFREY BULL