19635 W VANOWEN ST 91335
Certificate Information: 19635 W VANOWEN ST 91335
- Application / Permit
- 22016-20000-18207
- Plan Check / Job No.
- B22VN09437
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EXISTING REC. ROOM TO BE CONVERTED INTO ADU 371.66 S.F.
- Permit Issued
- Issued on 7/25/2022
- Issuing Office
- Current Status
- CofO Issued on 7/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | JOE VO |
| Corrections Issued | 7/11/2022 | JOE VO |
| Plan Check Approved | 7/20/2022 | JOE VO |
| Issued | 7/25/2022 | APPLICANT |
| CofO in Progress | 6/29/2023 | JEFFREY BULL |
| CofO in Progress | 7/13/2023 | SEAN WIRCH |
| CofO in Progress | 7/11/2024 | JEFFREY BULL |
| Permit Finaled | 7/11/2024 | JOHN JANSON |
| CofO Issued | 7/11/2024 | JOHN JANSON |
| Permit Finaled | 7/11/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 7/14/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 7/14/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 7/25/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/12/2022 | Approved | JEFFREY BULL |
| Deputy Drilled-In Anchors | 9/21/2022 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 9/21/2022 | Approved | JEFFREY BULL |
| Wood Frame | 9/21/2022 | Approved | JEFFREY BULL |
| HVAC-Rough | 9/29/2022 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 3/8/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 3/8/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 3/17/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 3/17/2023 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 3/17/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/21/2023 | Partial Approval | DAVID SANDOVAL |
| Insulation | 3/21/2023 | Partial Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 3/21/2023 | Corrections Issued | DAVID SANDOVAL |
| Drywall Nailing | 3/23/2023 | Approved | SEAN HAUPT |
| Final | 4/4/2023 | Not Ready for Inspection | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 4/4/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 4/4/2023 | Approved | JEFFREY BULL |
| Special/Order Compliance | 4/4/2023 | Partial Inspection | MORRIS JACKSON |
| Special/Order Compliance | 7/14/2023 | Corrections Issued | JEFFREY BULL |
| Final | 7/11/2024 | OK to Issue CofO | JEFFREY BULL |