5505-5507 N BURNET AVE 91411
Certificate Information: 5505-5507 N BURNET AVE 91411
- Application / Permit
- 22016-20000-18176
- Plan Check / Job No.
- B22VN09423
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT.
- Permit Issued
- Issued on 7/26/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 6/18/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 7/15/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 7/18/2022 | APPLICANT |
| Issued | 7/26/2022 | APPLICANT |
| CofO in Progress | 1/13/2023 | DAVID MATSON |
| CofO Issued | 1/18/2023 | MICHAEL SMITH |
| Permit Finaled | 1/18/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/1/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chatsky,, German; Lic. No.: C84153 | 3876 HUNTERS GROVE CT MOORPARK, CA 93021 |
Inspector Information
| DAVID ANDERSON, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/15/2022 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/30/2022 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 9/27/2022 | Corrections Issued | DAVID MATSON |
| Green Building Rough | 9/27/2022 | Not Ready for Inspection | DAVID MATSON |
| METHANE-Rough | 9/27/2022 | Not Ready for Inspection | DAVID MATSON |
| Rough-Elec/Plmb/HVAC | 9/27/2022 | Corrections Issued | DAVID MATSON |
| Sewer | 9/27/2022 | Approved | DAVID MATSON |
| BUILDING-Rough-Frame | 10/5/2022 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/5/2022 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/5/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| METHANE-Rough | 10/5/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/5/2022 | Not Ready for Inspection | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/12/2022 | Approved | THOMAS FINNILA |
| Green Building Rough | 10/12/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Rough | 10/12/2022 | Approved | THOMAS FINNILA |
| Drywall Nailing | 10/18/2022 | Approved | THOMAS FINNILA |
| Final | 11/14/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 11/14/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/14/2022 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 11/14/2022 | Approved | THOMAS FINNILA |
| Final | 11/21/2022 | Partial Approval | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Approved | THOMAS FINNILA |
| Final | 1/13/2023 | OK to Issue CofO | DAVID MATSON |