11742 N DE GARMO AVE 91340

Certificate Information: 11742 N DE GARMO AVE 91340

Application / Permit
22016-20000-18107
Plan Check / Job No.
B22VN09387
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO THE EXISTING A.D.U.
Permit Issued
Issued on 9/16/2022
Issuing Office
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/15/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 JOE VO
Corrections Issued 6/25/2022 JOE VO
Plan Check Approved 9/13/2022 JOE VO
Issued 9/16/2022 APPLICANT
CofO in Progress 9/5/2023 MICHEL ABAJAN
Permit Finaled 10/13/2023 RUBEN SALAS
CofO Issued 10/13/2023 RUBEN SALAS
Permit Finaled 10/13/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/9/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/13/2022 COLIN LOREDO
Sewer availability Cleared 9/15/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/2/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 11/2/2022 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 11/4/2022 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 12/5/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/31/2023 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 1/31/2023 Approved MICHEL ABAJAN
Green Building Rough 1/31/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 1/31/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 2/7/2023 Approved MICHEL ABAJAN
Green Building Rough 2/7/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/7/2023 Not Ready for Inspection MICHEL ABAJAN
Insulation 2/28/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/28/2023 Approved MICHEL ABAJAN
Drywall Nailing 3/14/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/1/2023 Approved MICHEL ABAJAN
Final 5/1/2023 Corrections Issued MICHEL ABAJAN
Green Building Final 5/1/2023 Approved MICHEL ABAJAN
HVAC-Final 5/1/2023 Approved MICHEL ABAJAN
PLUMBING-Final 5/1/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/1/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 5/1/2023 Approved MICHEL ABAJAN
Final 9/5/2023 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Approved MICHEL ABAJAN