4418 W 59TH PL 90043
Certificate Information: 4418 W 59TH PL 90043
- Application / Permit
- 22016-20000-17813
- Plan Check / Job No.
- B22VN09266
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) 19' X 19'-6" DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 8/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | PINANK PATEL |
| Corrections Issued | 6/22/2022 | PINANK PATEL |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Issued | 8/29/2022 | APPLICANT |
| CofO in Progress | 6/16/2023 | ENRIQUE MIRELES |
| CofO in Progress | 6/16/2023 | ENRIQUE MIRELES |
| Permit Finaled | 6/18/2023 | DEROLD HAUFF |
| CofO Issued | 6/18/2023 | DEROLD HAUFF |
| Permit Finaled | 6/18/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 6/24/2022 | KIRK LINKLATER |
| Address approval | Cleared | 6/27/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 6/27/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | JEANETTE VONG |
| Construction near power lines | Cleared | 8/12/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Better Together Builders Inc; Lic. No.: 1047689-B | 16430 VENTURA BLVD #304 ENCINO, CA 91436 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/20/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/26/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 9/28/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/13/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 10/13/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 10/13/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 10/13/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| METHANE-Rough | 10/13/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/13/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 10/25/2022 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 10/25/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 10/25/2022 | Partial Inspection | MICHAEL LEWIS |
| METHANE-Rough | 10/25/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 10/25/2022 | Corrections Issued | MICHAEL LEWIS |
| ELECTRICAL-Rough | 11/1/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/1/2022 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/1/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 11/8/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 11/22/2022 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 11/22/2022 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/16/2022 | Approved | ENRIQUE MIRELES |
| Final | 12/16/2022 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 12/16/2022 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/16/2022 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/16/2022 | Approved | ENRIQUE MIRELES |
| Final | 1/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 1/9/2023 | OK to Issue CofO | ENRIQUE MIRELES |