11572 N ACALA AVE 91340
Certificate Information: 11572 N ACALA AVE 91340
- Application / Permit
- 22016-20000-17768
- Plan Check / Job No.
- B22VN09226
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/14/2022
- Issuing Office
- Current Status
- CofO Issued on 4/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2022 | DANIEL YIP |
| Corrections Issued | 6/28/2022 | DANIEL YIP |
| Plan Check Approved | 7/13/2022 | DANIEL YIP |
| Issued | 7/14/2022 | APPLICANT |
| CofO in Progress | 4/19/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
| CofO Issued | 4/19/2023 | MICHAEL SMITH |
| Permit Finaled | 4/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/1/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 7/1/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 7/5/2022 | LEE GUILBEAUX |
| Grading Pre-Inspection | Cleared | 7/13/2022 | ROBERT HUGHES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/18/2022 | Partial Inspection | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 8/30/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 9/6/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/6/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 10/6/2022 | Partial Approval | DEANDRE HOFFMAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Approved | DEANDRE HOFFMAN |
| Gas Test | 10/6/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 10/6/2022 | Partial Approval | DEANDRE HOFFMAN |
| Sewer | 10/6/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 10/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 10/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 10/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 10/31/2022 | Approved | JENNIFER RABUCHIN |
| Wood Frame | 10/31/2022 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 11/9/2022 | Partial Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 11/9/2022 | Approved | JENNIFER RABUCHIN |
| Gas Test | 11/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 11/9/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 11/9/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| MERV13>=Rough | 11/9/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/9/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 11/23/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/7/2022 | Approved | JENNIFER RABUCHIN |
| Pre-Inspection | 1/3/2023 | Partial Inspection | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 1/23/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 1/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 1/23/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/23/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 1/23/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 1/30/2023 | Approved | JENNIFER RABUCHIN |
| Final | 1/30/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 1/30/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 1/30/2023 | Approved | JENNIFER RABUCHIN |