13022 W GARBER ST 91331

Certificate Information: 13022 W GARBER ST 91331

Application / Permit
22016-20000-17670
Plan Check / Job No.
B22VN09172
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) DETACHED STORAGE TO (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 8/24/2022
Issuing Office
Current Status
CofO Issued on 3/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2022 APPLICANT
Assigned to Plan Check Engineer 6/29/2022 DANIEL YIP
Corrections Issued 6/30/2022 DANIEL YIP
Applicant returned to address corrections 7/27/2022 DANIEL YIP
Plan Check Approved 8/19/2022 DANIEL YIP
Issued 8/24/2022 APPLICANT
CofO in Progress 2/7/2024 MISAEL ESPARZA
Permit Finaled 3/6/2024 RUBEN SALAS
CofO Issued 3/6/2024 RUBEN SALAS
Permit Finaled 3/6/2024 RUBEN SALAS

Permit Application Clearance Information

Sewer availability Cleared 7/27/2022 MEGAN GODINEZ
Address approval Cleared 7/28/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/28/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 7/28/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 7/28/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 7/28/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Mauricio,, Omar; Lic. No.: C87487 947 E MERCED AVE      WEST COVINA, CA 91790
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2022 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 12/1/2022 Approved MICHEL ABAJAN
ELECTRICAL-Rough 1/9/2023 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 1/9/2023 Not Ready for Inspection KIRK SANDERS
Sewer 1/9/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 1/12/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 1/12/2023 Partial Approval MICHEL ABAJAN
Sewer 1/12/2023 Not Ready for Inspection MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/17/2023 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 1/17/2023 Approved MICHEL ABAJAN
Sewer 1/17/2023 Not Ready for Inspection MICHEL ABAJAN
Wood Frame 1/20/2023 Not Ready for Inspection ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 1/27/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 1/27/2023 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 2/3/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/3/2023 Approved MICHEL ABAJAN
METHANE-Rough 2/3/2023 Approved MICHEL ABAJAN
Underground Mechanical 2/3/2023 Partial Approval MICHEL ABAJAN
Insulation 2/7/2023 Approved MICHEL ABAJAN
Underground Mechanical 2/7/2023 Approved MICHEL ABAJAN
Drywall Nailing 3/7/2023 Approved MICHEL ABAJAN
HVAC-Rough 3/7/2023 Partial Approval MICHEL ABAJAN
Underground Mechanical 3/7/2023 Partial Approval MICHEL ABAJAN
ELECTRICAL-Final 3/10/2023 No Access for Inspection MICHEL ABAJAN
Final 3/10/2023 No Access for Inspection MICHEL ABAJAN
HVAC-Final 3/10/2023 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 3/10/2023 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/10/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 3/10/2023 No Access for Inspection MICHEL ABAJAN
Shower Pan 7/18/2023 Corrections Issued MICHEL ABAJAN
Shower Pan 7/24/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/26/2023 Approved MISAEL ESPARZA
ELECTRICAL-Final 1/18/2024 Approved MICHEL ABAJAN
Final 1/18/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 1/18/2024 Approved MICHEL ABAJAN
PLUMBING-Final 1/18/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/18/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/18/2024 Corrections Issued MICHEL ABAJAN
Final 2/6/2024 OK to Issue CofO MISAEL ESPARZA
Smoke Detectors 2/6/2024 Approved MISAEL ESPARZA