2236 S ALSACE AVE 90016

Certificate Information: 2236 S ALSACE AVE 90016

Application / Permit
22016-20000-17637
Plan Check / Job No.
B22VN09143
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 12'-0" X 7'-0" PORTION OF (E) GARAGE TO STORAGE AND CONVERT REMANING PORTION OF GARAGE, (E) REC ROOM & STORAGE INTO A (N) ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 9/12/2022
Issuing Office
Metro
Current Status
CofO Issued on 10/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2022 APPLICANT
Assigned to Plan Check Engineer 6/13/2022 ARTIN ZARUKIAN
Corrections Issued 6/13/2022 ARTIN ZARUKIAN
Building Plans Picked Up 6/15/2022 APPLICANT
Plan Check Approved 9/12/2022 DANIEL SANJUAN
Issued 9/12/2022 APPLICANT
CofO in Progress 10/26/2023 WILLIAM MICHALAK
Permit Finaled 10/31/2023 BRUCE TODD
CofO Issued 10/31/2023 BRUCE TODD
Permit Finaled 10/31/2023 BRUCE TODD

Permit Application Clearance Information

Construction near power lines Cleared 8/25/2022 RIDWAN HARDY
Address approval Cleared 9/3/2022 JEANETTE VONG
Sewer availability Cleared 9/3/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 9/8/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2022 Approved WILLIAM MICHALAK
Pre-Inspection 2/1/2023 Approved WILLIAM MICHALAK
Insulation 3/29/2023 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 3/29/2023 Approved WILLIAM MICHALAK
PLUMBING-Rough 3/29/2023 Approved WILLIAM MICHALAK
Drywall Nailing 4/14/2023 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 4/14/2023 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 4/14/2023 Approved WILLIAM MICHALAK
ELECTRICAL-Rough 4/26/2023 Approved WILLIAM MICHALAK
Service/Power Release 4/26/2023 Not Ready for Inspection WILLIAM MICHALAK
BUILDING-Rough-Frame 6/28/2023 Corrections Issued WILLIAM MICHALAK
Final 6/28/2023 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 6/28/2023 Not Ready for Inspection WILLIAM MICHALAK
MERV13>=Final 6/28/2023 Approved WILLIAM MICHALAK
MERV13>=Rough 6/28/2023 Approved WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 6/28/2023 SGSOV Approved WILLIAM MICHALAK
Smoke Detectors 6/28/2023 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 7/6/2023 Approved WILLIAM MICHALAK
Final 7/6/2023 Corrections Issued WILLIAM MICHALAK
Green Building Final 7/6/2023 Approved WILLIAM MICHALAK
Final 9/8/2023 Conditional Approval WILLIAM MICHALAK
Final 10/26/2023 Conditional Approval WILLIAM MICHALAK