17215 W KESWICK ST 91406

Certificate Information: 17215 W KESWICK ST 91406

Application / Permit
22016-20000-17473
Plan Check / Job No.
B22VN09022
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT CONVERT DETACHED GARAGE TO ADU PER STATE LAW ALL WORK DONE PER WFPP
Permit Issued
Issued on 8/19/2022
Issuing Office
Current Status
CofO Issued on 5/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2022 APPLICANT
Assigned to Plan Check Engineer 6/17/2022 KHUONG TRUONG
Corrections Issued 6/19/2022 KHUONG TRUONG
Plan Check Approved 8/18/2022 KHUONG TRUONG
Issued 8/19/2022 APPLICANT
CofO in Progress 5/18/2023 JENNIFER RABUCHIN
CofO Issued 5/22/2023 MICHAEL SMITH
Permit Finaled 5/22/2023 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 8/12/2022 RIDWAN HARDY
Address approval Cleared 8/15/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/15/2022 COLIN LOREDO
Sewer availability Cleared 8/15/2022 COLIN LOREDO

Contact Information

Contractor Flip It Homes Inc; Lic. No.: 1043456-B       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/30/2022 Corrections Issued RAUL OLAGI
Sewer 9/30/2022 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 10/6/2022 Approved RAUL OLAGI
Footing/Foundation/Slab 10/6/2022 Approved RAUL OLAGI
PLUMBING-Rough 10/6/2022 Partial Approval RAUL OLAGI
Special/Order Compliance 10/6/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 11/8/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 11/8/2022 Corrections Issued RAUL OLAGI
Green Building Rough 11/8/2022 Not Ready for Inspection RAUL OLAGI
HVAC-Rough 11/8/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 11/8/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 11/15/2022 Approved RAUL OLAGI
HVAC-Rough 11/15/2022 Approved RAUL OLAGI
PLUMBING-Rough 11/15/2022 Approved RAUL OLAGI
Wood Frame 11/15/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 11/28/2022 Partial Approval RAUL OLAGI
Green Building Rough 11/28/2022 Approved RAUL OLAGI
Insulation 11/28/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 11/28/2022 Approved RAUL OLAGI
Drywall Nailing 12/8/2022 Partial Approval RAUL OLAGI
Drywall Nailing 12/19/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 12/19/2022 Approved RAUL OLAGI
Shower Pan 12/19/2022 Approved RAUL OLAGI
Pre-Inspection 3/30/2023 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 5/12/2023 Approved RAUL OLAGI
Final 5/12/2023 Corrections Issued RAUL OLAGI
Green Building Final 5/12/2023 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 5/12/2023 SGSOV Not Ready RAUL OLAGI
Smoke Detectors 5/12/2023 Approved RAUL OLAGI
ELECTRICAL-Final 5/17/2023 Approved JENNIFER RABUCHIN
Final 5/17/2023 OK to Issue CofO JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 5/17/2023 SGSOV Approved JENNIFER RABUCHIN