22141 W COVELLO ST 91303

Certificate Information: 22141 W COVELLO ST 91303

Application / Permit
22016-20000-17469
Plan Check / Job No.
B22VN09019
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE INTO AN ADU.
Permit Issued
Issued on 7/27/2022
Issuing Office
Current Status
CofO Issued on 5/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2022 APPLICANT
Assigned to Plan Check Engineer 6/15/2022 JOE VO
Corrections Issued 6/16/2022 JOE VO
Plan Check Approved 6/29/2022 JOE VO
Issued 7/27/2022 APPLICANT
CofO in Progress 8/28/2023 CHRIS CHRISTENSEN
Permit Finaled 5/17/2024 DANIEL ORRANTE
CofO Issued 5/17/2024 DANIEL ORRANTE
Permit Finaled 5/17/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/22/2022 MEGAN GODINEZ
Sewer availability Cleared 6/22/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/23/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/23/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/23/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/23/2022 MEGAN GODINEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/12/2022 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 9/19/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/19/2022 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 9/23/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 9/23/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 9/23/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 9/23/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 9/23/2022 Approved CHRIS CHRISTENSEN
HVAC-Rough 10/3/2022 Approved CHRIS CHRISTENSEN
Insulation 10/3/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/3/2022 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/11/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/11/2022 Conditional Approval CHRIS CHRISTENSEN
Insulation 10/11/2022 Approved CHRIS CHRISTENSEN
Drywall Nailing 10/17/2022 Approved CHRIS CHRISTENSEN
Green Building Rough 10/17/2022 Approved CHRIS CHRISTENSEN
Shower Pan 10/17/2022 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/24/2022 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 4/28/2023 No Access for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 5/16/2023 Corrections Issued CHRIS CHRISTENSEN
Final 5/16/2023 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 5/16/2023 Approved CHRIS CHRISTENSEN
PLUMBING-Final 5/16/2023 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 5/16/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/22/2023 Approved CHRIS CHRISTENSEN
Final 5/22/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 5/22/2023 SGSOV Approved CHRIS CHRISTENSEN
Final 8/25/2023 OK to Issue CofO CHRIS CHRISTENSEN