22141 W COVELLO ST 91303
Certificate Information: 22141 W COVELLO ST 91303
- Application / Permit
- 22016-20000-17469
- Plan Check / Job No.
- B22VN09019
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE INTO AN ADU.
- Permit Issued
- Issued on 7/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/15/2022 | JOE VO |
| Corrections Issued | 6/16/2022 | JOE VO |
| Plan Check Approved | 6/29/2022 | JOE VO |
| Issued | 7/27/2022 | APPLICANT |
| CofO in Progress | 8/28/2023 | CHRIS CHRISTENSEN |
| Permit Finaled | 5/17/2024 | DANIEL ORRANTE |
| CofO Issued | 5/17/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/17/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/22/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 6/22/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/23/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/23/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/23/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/23/2022 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/12/2022 | Corrections Issued | DAVID SANDOVAL |
| Footing/Foundation/Slab | 9/19/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/19/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/23/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 9/23/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 9/23/2022 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/23/2022 | Approved | CHRIS CHRISTENSEN |
| Pre-Inspection | 9/23/2022 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/3/2022 | Approved | CHRIS CHRISTENSEN |
| Insulation | 10/3/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/3/2022 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 10/11/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/11/2022 | Conditional Approval | CHRIS CHRISTENSEN |
| Insulation | 10/11/2022 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 10/17/2022 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 10/17/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 10/17/2022 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 4/28/2023 | No Access for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/16/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 5/16/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 5/16/2023 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 5/16/2023 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2023 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/16/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/22/2023 | Approved | CHRIS CHRISTENSEN |
| Final | 5/22/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/22/2023 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 8/25/2023 | OK to Issue CofO | CHRIS CHRISTENSEN |