5250 N BELLAIRE AVE 91607
Certificate Information: 5250 N BELLAIRE AVE 91607
- Application / Permit
- 22016-20000-17333
- Plan Check / Job No.
- B22VN08963
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2-CAR GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Current Status
- CofO Issued on 1/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 7/9/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 7/21/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 7/25/2022 | APPLICANT |
| Plan Check Approved | 8/31/2022 | MOHAMMAD ESMAILI |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 12/1/2023 | JUAN VALENZUELA |
| Permit Finaled | 1/5/2024 | RUBEN SALAS |
| CofO Issued | 1/5/2024 | RUBEN SALAS |
| Permit Finaled | 1/5/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2022 | ROMAN GUTIERREZ |
| Roof/Waste drainage to street | Cleared | 7/29/2022 | ROMAN GUTIERREZ |
| Construction near power lines | Cleared | 8/1/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 8/2/2022 | ROMAN GUTIERREZ |
| Specific Plan | Cleared | 8/8/2022 | CORREY KITCHENS |
| ZI | Cleared | 8/8/2022 | CORREY KITCHENS |
Contact Information
| Contractor | K T Construction & Development; Lic. No.: 1031495-B | 137 SOUTH ROBERTSON BLVD BEVERLY HILLS, CA 90211 |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 1792 PEREGRINE CT SIMI VALLEY, CA 93065 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/30/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 1/30/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Rough | 5/22/2023 | Approved | KIRK SANDERS |
| PLUMBING-Rough | 5/22/2023 | Approved | KIRK SANDERS |
| Underground Mechanical | 5/22/2023 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 6/1/2023 | Approved | KIRK SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 6/1/2023 | Approved | KIRK SANDERS |
| Green Building Rough | 6/1/2023 | Approved | KIRK SANDERS |
| HVAC-Rough | 6/1/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 6/13/2023 | Approved | JOHN COLEMAN |
| Insulation | 6/23/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 7/10/2023 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 7/21/2023 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 10/24/2023 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 11/21/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 11/21/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Gas Test | 11/21/2023 | Approved | JUAN VALENZUELA |
| Green Building Final | 11/21/2023 | Approved | JUAN VALENZUELA |
| HVAC-Final | 11/21/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 11/21/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/21/2023 | SGSOV Approved | JUAN VALENZUELA |
| Service/Power Release | 11/21/2023 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 11/21/2023 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/1/2023 | Approved | JUAN VALENZUELA |
| Final | 12/1/2023 | OK to Issue CofO | JUAN VALENZUELA |
| HVAC-Final | 12/1/2023 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 12/1/2023 | Approved | JUAN VALENZUELA |
| Service/Power Release | 12/1/2023 | Approved | JUAN VALENZUELA |