1608 1/2 N WESTERLY TER 90026

Certificate Information: 1608 1/2 N WESTERLY TER 90026

Application / Permit
22016-20000-17097
Plan Check / Job No.
B22VN08809
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT EXISTING STORAGE AND MECHANICAL ROOM OF THE EXISTING THREE STORY DUPLEX INTO ACCESSORY DWELLING UNIT PER Multiple ADUs per State Law GCS 65852.2(e)(1)(C) - NO CHANGE IN STRUCTURAL
Permit Issued
Issued on 9/19/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2022 APPLICANT
Assigned to Plan Check Engineer 6/8/2022 DANIEL ABRAMYAN
Corrections Issued 6/8/2022 DANIEL ABRAMYAN
Building Plans Picked Up 6/10/2022 APPLICANT
Plan Check Approved 9/19/2022 AUNG SOE
Issued 9/19/2022 APPLICANT
CofO in Progress 2/10/2023 THOMAS LOGRASSO
Permit Finaled 2/14/2023 DEROLD HAUFF
CofO Issued 2/14/2023 DEROLD HAUFF
Permit Finaled 2/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Street Frontage Cleared 8/19/2022 AMAAN MALIK
Address approval Cleared 8/22/2022 JEANETTE VONG
Sewer availability Cleared 8/22/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 8/23/2022 JEANETTE VONG
Encroachment in public way Cleared 8/26/2022 MARYAM SAEDI
Tenant Habitability Plan Cleared 9/1/2022 RICARDO BOHORQUEZ

Contact Information

Architect Osinski,, Tomas Kazimierz; Lic. No.: C22658 4240 GLENMUIR AVE      LOS ANGELES, CA 90065
Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/26/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Rough 10/26/2022 Corrections Issued THOMAS LOGRASSO
Green Building Rough 10/26/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Rough 10/26/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 10/26/2022 Conditional Approval THOMAS LOGRASSO
Special/Order Compliance 10/26/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 11/3/2022 Approved THOMAS LOGRASSO
Green Building Rough 11/3/2022 Approved THOMAS LOGRASSO
Insulation 11/3/2022 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 11/3/2022 Approved THOMAS LOGRASSO
Drywall Nailing 11/21/2022 Approved DONALD CRICHLOW
ELECTRICAL-Final 1/24/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 1/24/2023 Corrections Issued THOMAS LOGRASSO
Green Building Final 1/24/2023 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/24/2023 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 1/24/2023 Approved THOMAS LOGRASSO
Final 2/9/2023 OK to Issue CofO THOMAS LOGRASSO
Green Building Final 2/9/2023 Approved THOMAS LOGRASSO