6935 W FOOTHILL BLVD 91042
Certificate Information: 6935 W FOOTHILL BLVD 91042
- Application / Permit
- 22016-20000-16808
- Plan Check / Job No.
- B22VN08661
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ePlan T.I. Change of use from retail to a restaurant for new Arnie's Bakery. and provide 1 disabled access stall
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2022 | LUKE GONZALES |
| Corrections Issued | 6/7/2022 | LUKE GONZALES |
| Plan Check Approved | 10/6/2022 | ADAM HEGAZI |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 4/4/2024 | ANDREW DORSO |
| Permit Finaled | 4/8/2024 | JEFFREY DURAN |
| CofO Issued | 4/8/2024 | JEFFREY DURAN |
| Permit Finaled | 4/8/2024 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 6/23/2022 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 7/6/2022 | JOSE DUARTE-DIAZ |
| Food Service Establishment | Cleared | 9/13/2022 | PAWAN VERMA |
| Specific Plan | Cleared | 9/29/2022 | WILLIAM CABRERA |
| Food establishment approval | Cleared | 10/5/2022 | LACDHS APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/11/2022 | Partial Inspection | ANDREW DORSO |
| Wood Frame | 10/11/2022 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 11/7/2022 | Not Ready for Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 11/10/2022 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 11/10/2022 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 11/14/2022 | Approved | ANDREW DORSO |
| Footing/Foundation/Slab | 5/11/2023 | Partial Inspection | ANDREW DORSO |
| Deputy Drilled-In Anchors | 6/21/2023 | Conditional Approval | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 3/5/2024 | SGSOV Not Ready | ANDREW DORSO |
| Smoke Detectors | 3/5/2024 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 3/5/2024 | Approved | ANDREW DORSO |
| Wood Frame | 3/5/2024 | Approved | ANDREW DORSO |
| Final | 3/18/2024 | Partial Inspection | ANDREW DORSO |
| Final | 4/1/2024 | Partial Approval | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 4/1/2024 | SGSOV Approved | ANDREW DORSO |
| Final | 4/4/2024 | OK to Issue CofO | ANDREW DORSO |