7831 S WESTLAWN AVE 90045
Certificate Information: 7831 S WESTLAWN AVE 90045
- Application / Permit
- 22016-20000-16757
- Plan Check / Job No.
- B22VN08629
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATT. 2-CAR GARAGE (364 SF) INTO JUNIOR ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) AND 65852.22 - ALL WORK PER WFPP
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Current Status
- CofO Issued on 11/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/2/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2022 | DANIEL ABRAMYAN |
| Corrections Issued | 6/4/2022 | DANIEL ABRAMYAN |
| Building Plans Picked Up | 6/8/2022 | APPLICANT |
| Issued | 6/16/2022 | APPLICANT |
| CofO in Progress | 11/3/2022 | BOBBY KEY |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
| CofO Issued | 11/3/2022 | DANIEL ORRANTE |
| Permit Finaled | 11/3/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/14/2022 | JENSON LEE |
| Address approval | Cleared | 6/16/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2022 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2022 | Partial Inspection | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 6/28/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 6/28/2022 | Partial Approval | BOBBY KEY |
| Final | 7/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 7/6/2022 | Corrections Issued | STEPHANIE SWANSON |
| Rough-Elec/Plmb/HVAC | 7/11/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 7/12/2022 | Approved | BOBBY KEY |
| Insulation | 7/13/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 7/15/2022 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 7/19/2022 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Approved | RICHARD STEINBACH |
| Green Building Rough | 7/19/2022 | Approved | RICHARD STEINBACH |
| Shower Pan | 7/19/2022 | Approved | RICHARD STEINBACH |
| SGSOV-Seismic Gas S/O Valve | 9/13/2022 | SGSOV Not Ready | BOBBY KEY |
| ELECTRICAL-Final | 9/22/2022 | Corrections Issued | BOBBY KEY |
| Final | 9/22/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Final | 9/22/2022 | Approved | BOBBY KEY |
| HVAC-Final | 9/22/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/22/2022 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/22/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 9/22/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/2/2022 | Approved | BOBBY KEY |
| Final | 11/2/2022 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 11/2/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 11/2/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 11/2/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 11/2/2022 | Approved | BOBBY KEY |