10931 N OSO AVE 91311
Certificate Information: 10931 N OSO AVE 91311
- Application / Permit
- 22016-20000-16714
- Plan Check / Job No.
- B22VN08591
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO REMOVE INTERIOR WALLS TO ENLARGE AND REMODEL (E) KITCHEN. ADD NEW INTERIOR SHEAR WALLS AT THE FIRST FLOOR OF (E) TWO STORY SINGLE-FAMILY DWELLING PER ENGINEER.
- Permit Issued
- Issued on 9/19/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 4/5/2023
Permit Application Status History
| Submitted | 6/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2022 | JEROME MAGAT PALMA |
| Corrections Issued | 6/7/2022 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 8/26/2022 | APPLICANT |
| Plan Check Approved | 9/19/2022 | LUIS RINCON |
| Issued | 9/19/2022 | APPLICANT |
| Permit Finaled | 4/5/2023 | DAVID SCANTLIN |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/12/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Hands On Remodeling Inc; Lic. No.: 542536-B | 21860 BURBANK BLVD STE 170-N WOODLAND HILLS, CA 91367 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/7/2022 | Conditional Approval | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 11/7/2022 | Approved | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 11/23/2022 | Not Ready for Inspection | JOHN KIDWELL |
| Special/Order Compliance | 11/23/2022 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 12/9/2022 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/9/2022 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/9/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/15/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/15/2022 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 12/15/2022 | Approved | JOHN KIDWELL |
| Special/Order Compliance | 12/15/2022 | Partial Inspection | MORRIS JACKSON |
| BUILDING-Rough-Frame | 1/3/2023 | Approved | JOHN KIDWELL |
| HVAC-Rough | 1/3/2023 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 1/3/2023 | Partial Approval | JOHN KIDWELL |
| Pre-Inspection | 1/3/2023 | Partial Inspection | JUSTIN HAWLEY |
| Drywall Nailing | 1/11/2023 | Approved | DAVID SCANTLIN |
| Insulation | 1/11/2023 | Approved | DAVID SCANTLIN |
| PLUMBING-Final | 2/15/2023 | Approved | MORRIS JACKSON |
| Final | 4/5/2023 | Permit Finaled | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/5/2023 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 4/5/2023 | Approved | DAVID SCANTLIN |