10513 N AMBOY AVE 91331

Certificate Information: 10513 N AMBOY AVE 91331

Application / Permit
22016-20000-16712
Plan Check / Job No.
B22VN08589
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Addition to existing detached garage and convert to new ADU per WFPP (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 10/4/2022
Issuing Office
Current Status
CofO Issued on 6/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2022 APPLICANT
Assigned to Plan Check Engineer 6/13/2022 AUNG SOE
Plan Check Approved 9/30/2022 ADAM HEGAZI
Issued 10/4/2022 APPLICANT
CofO in Progress 6/11/2024 ROBERT GOLD
Permit Finaled 6/21/2024 RUBEN SALAS
CofO Issued 6/21/2024 RUBEN SALAS
Permit Finaled 6/21/2024 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 6/22/2022 MIGUEL GAMBOA
Address approval Cleared 6/23/2022 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/23/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 6/25/2022 MEGAN GODINEZ
Sewer availability Cleared 6/25/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 6/25/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 6/25/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 6/25/2022 MEGAN GODINEZ
Construction near power lines Cleared 7/27/2022 TINA MIRANDA
Construction within easement Cleared 7/27/2022 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/20/2023 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 12/12/2023 Approved MICHEL ABAJAN
METHANE-Barrier 12/12/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 12/12/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 12/12/2023 Partial Approval MICHEL ABAJAN
Underground Mechanical 12/12/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Approval MICHEL ABAJAN
Green Building Rough 2/7/2024 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 2/7/2024 Approved MICHEL ABAJAN
Sewer 2/7/2024 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 2/28/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 2/28/2024 Approved MICHEL ABAJAN
Green Building Rough 2/28/2024 Approved MICHEL ABAJAN
HVAC-Rough 2/28/2024 Approved MICHEL ABAJAN
Insulation 3/5/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/5/2024 Approved MICHEL ABAJAN
Drywall Nailing 3/8/2024 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/8/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 5/10/2024 Approved MICHEL ABAJAN
Final 5/10/2024 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 5/10/2024 Approved MICHEL ABAJAN
HVAC-Final 5/10/2024 Approved MICHEL ABAJAN
PLUMBING-Final 5/10/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 5/10/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 5/10/2024 Approved MICHEL ABAJAN
Final 5/15/2024 OK to Issue CofO MICHEL ABAJAN