6052 N CASE AVE 91606
Certificate Information: 6052 N CASE AVE 91606
- Application / Permit
- 22016-20000-16502
- Plan Check / Job No.
- B22VN08419
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: CONVERT ONE STORY GARAGE INTO ADU PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/30/2022
- Issuing Office
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | RICARDO RAMIREZ |
| Corrections Issued | 6/10/2022 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 6/16/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 6/28/2022 | RICARDO RAMIREZ |
| Issued | 6/30/2022 | APPLICANT |
| CofO in Progress | 9/5/2023 | JOHN HAYES |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/10/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/10/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 10/19/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 10/25/2022 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 11/1/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 12/8/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 12/8/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 12/8/2022 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 12/8/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 1/31/2023 | Corrections Issued | DAVID ANDERSON |
| BUILDING-Rough-Frame | 2/23/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 2/23/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 2/23/2023 | Approved | JOHN HAYES |
| PLUMBING-Rough | 2/23/2023 | Approved | JOHN HAYES |
| Special/Order Compliance | 2/23/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 3/2/2023 | Approved | JOHN HAYES |
| Insulation | 3/2/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 3/2/2023 | Partial Approval | JOHN HAYES |
| Shower Pan | 3/2/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 3/15/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 3/15/2023 | Approved | MISAEL ESPARZA |
| Final | 8/23/2023 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 8/23/2023 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 8/23/2023 | Approved | JOHN HAYES |
| Final | 9/5/2023 | OK to Issue CofO | JOHN HAYES |