16020 W JERSEY ST 91344

Certificate Information: 16020 W JERSEY ST 91344

Application / Permit
22016-20000-16500
Plan Check / Job No.
B22VN08416
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX 18'X20' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). ALL WORK PER WFPP.
Permit Issued
Issued on 10/27/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/1/2022 HAYATO TSUCHIYA
Building Plans Picked Up 6/2/2022 APPLICANT
Corrections Issued 8/17/2022 HAYATO TSUCHIYA
Applicant returned to address corrections 9/8/2022 LUISANGEL VALENZUELA
Plan Check Approved 10/27/2022 MIROOSH KHACHATOORIAN
Issued 10/27/2022 APPLICANT
CofO in Progress 3/10/2023 JAVIER RAMOS JR
Permit Finaled 4/4/2023 DANIEL ORRANTE
CofO Issued 4/4/2023 DANIEL ORRANTE
Permit Finaled 4/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/27/2022 CARLOS AGUILERA
Sewer availability Cleared 6/27/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/29/2022 CARLOS AGUILERA
Construction near power lines Cleared 9/19/2022 PATRICK MAGALLANES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/3/2022 Partial Approval JAVIER RAMOS JR
Sewer 11/3/2022 Corrections Issued JAVIER RAMOS JR
Underground Mechanical 11/3/2022 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/17/2022 Approved JAVIER RAMOS JR
Sewer 11/17/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 11/22/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 11/22/2022 Not Ready for Inspection JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/22/2022 Partial Inspection JAVIER RAMOS JR
MERV13>=Rough 11/22/2022 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 11/22/2022 Approved JAVIER RAMOS JR
Pre-Inspection 11/22/2022 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 12/2/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 12/2/2022 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 12/2/2022 Approved JAVIER RAMOS JR
Green Building Rough 12/2/2022 Approved JAVIER RAMOS JR
HVAC-Rough 12/2/2022 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 12/2/2022 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 12/2/2022 Approved JAVIER RAMOS JR
PLUMBING-Rough 12/2/2022 Approved JAVIER RAMOS JR
Insulation 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 12/9/2022 Partial Inspection CHRISTOPHER DELLEFIELD
Shower Pan 12/9/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 12/16/2022 Approved JAVIER RAMOS JR
Drywall Nailing 12/16/2022 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 12/16/2022 Approved JAVIER RAMOS JR
Green Building Rough 12/16/2022 Approved JAVIER RAMOS JR
HVAC-Rough 12/16/2022 Approved JAVIER RAMOS JR
Drywall Nailing 12/22/2022 Approved JAVIER RAMOS JR
Insulation 12/22/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 12/22/2022 Approved JAVIER RAMOS JR
Shower Pan 12/22/2022 Approved JAVIER RAMOS JR
Final 2/9/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 2/9/2023 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Final 2/9/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 2/9/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 3/8/2023 Approved JAVIER RAMOS JR
Final 3/8/2023 OK to Issue CofO JAVIER RAMOS JR
Green Building Final 3/8/2023 Approved JAVIER RAMOS JR
HVAC-Final 3/8/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 3/8/2023 Approved JAVIER RAMOS JR