18000 W DEVONSHIRE ST 91325

Certificate Information: 18000 W DEVONSHIRE ST 91325

Application / Permit
22016-20000-16238
Plan Check / Job No.
B22VN08288
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
(ePlan) New exterior fabric sunshade structure located at the existing west quad of the Medtronic campus.
Permit Issued
Issued on 3/21/2023
Issuing Office
Current Status
CofO Issued on 4/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/31/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 YOUNG KIM
Corrections Issued 7/11/2022 YOUNG KIM
Quality Review Completed 7/12/2022 FARUK SEZER
Applicant returned to address corrections 10/19/2022 YOUNG KIM
Applicant returned to address corrections 10/25/2022 YOUNG KIM
Applicant returned to address corrections 11/22/2022 YOUNG KIM
Applicant returned to address corrections 1/24/2023 YOUNG KIM
Applicant returned to address corrections 1/27/2023 YOUNG KIM
Plan Check Approved 2/15/2023 YOUNG KIM
Issued 3/21/2023 APPLICANT
CofO in Progress 3/11/2024 GREGORY POMISH
Permit Finaled 4/5/2024 JEFFREY DURAN
CofO Issued 4/5/2024 JEFFREY DURAN
Permit Finaled 4/5/2024 JEFFREY DURAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/22/2022 JOSE DUARTE-DIAZ
Miscellaneous Cleared 8/22/2022 NOAH MCCOY
Low Impact Development Cleared 11/6/2022 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/8/2022 DAGOVERTO GUERRERO
Fire Marshal Fire Life Safety Cleared 12/21/2022 MENOA AGHAJANI
Miscellaneous Cleared 12/21/2022 MENOA AGHAJANI

Contact Information

Architect Kluger,, Charles Edward; Lic. No.: NA24283       ,
Contractor Csa Constructors Inc; Lic. No.: 341470-B       ,
Engineer Mitchell,, James Lawrence; Lic. No.: S3081 3707 EL JAMES DR      SPRING, TX 77388

Inspector Information

GREGORY POMISH, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI
EDWIN GREGORYONA, (818) 374-3303 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/29/2023 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/20/2023 Partial Inspection DEANDRE HOFFMAN
Footing/Foundation/Slab 10/11/2023 Partial Inspection JEFFREY FULTON
Final 10/30/2023 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 10/30/2023 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 10/30/2023 SGSOV Approved JEFFREY FULTON
Smoke Detectors 10/30/2023 Approved JEFFREY FULTON
Verify Sprinkler Sign Off 10/30/2023 Approved JEFFREY FULTON
Wood Frame 10/30/2023 Approved JEFFREY FULTON
Final 3/11/2024 OK to Issue CofO GREGORY POMISH