5239 N WILKINSON AVE 1-4 91607
Certificate Information: 5239 N WILKINSON AVE 1-4 91607
- Application / Permit
- 22016-20000-16180
- Plan Check / Job No.
- B22VN08255
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: Convert first floor laundry & storage room in 2-story, 3-unit Apartment House to one Studio ADU (20x15).
- Permit Issued
- Issued on 8/1/2022
- Issuing Office
- Current Status
- CofO Issued on 7/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | JESSE JIMENEZ |
| Corrections Issued | 6/1/2022 | JESSE JIMENEZ |
| Applicant returned to address corrections | 7/19/2022 | JESSE JIMENEZ |
| Plan Check Approved | 7/21/2022 | JESSE JIMENEZ |
| Issued | 8/1/2022 | APPLICANT |
| CofO in Progress | 7/17/2023 | ROBERT DAVIS |
| Permit Finaled | 7/17/2023 | JEFFREY DURAN |
| CofO Issued | 7/17/2023 | JEFFREY DURAN |
| Permit Finaled | 7/17/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/2/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 6/22/2022 | CORREY KITCHENS |
| Tenant Habitability Plan | Cleared | 7/7/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/11/2022 | Corrections Issued | ROBERT DAVIS |
| Wood Frame | 4/13/2023 | Partial Approval | ROBERT DAVIS |
| Insulation | 4/17/2023 | Approved | ROBERT DAVIS |
| Drywall Nailing | 4/21/2023 | Approved | ROBERT DAVIS |
| Interior/Exterior Lathing | 4/21/2023 | Approved | ROBERT DAVIS |
| Final | 7/12/2023 | OK to Issue CofO | ROBERT DAVIS |
| Green Building Final | 7/12/2023 | Approved | ROBERT DAVIS |
| Green Building Rough | 7/12/2023 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/12/2023 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 7/12/2023 | Approved | ROBERT DAVIS |
| Wood Frame | 7/12/2023 | Approved | ROBERT DAVIS |